Interconnection queue in MISO (Midcontinent) (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown13623.7 GW
Active in queue23.7 GW136 requests
Agreement signed1,055 MW8 requests
Withdrawn26738.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

136 requests Β· page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2261, Jackson County
Solar
625 MWIn study Jackson, ARMISO Oct 2021target 2028
Solar project J2262, Jackson County
Solar
625 MWIn study Jackson, ARMISO Oct 2021target 2028
Solar + storage project J1897, Mississippi County
Solar + storage
500 MWIn study Mississippi, ARMISO Dec 2021target 2027
Solar + storage project J1899, Mississippi County
Solar + storage
500 MWIn study Mississippi, ARMISO Dec 2021target 2027
Solar + storage project J2190, Mississippi County
Solar + storage
500 MWIn study Mississippi, ARMISO Aug 2021target 2027
Solar project J1855, Jackson County
Solar
500 MWIn study Jackson, ARMISO Nov 2021target 2026
Solar project J1858, Mississippi County
Solar
440 MWIn study Mississippi, ARMISO Nov 2021target 2028
Solar project J2268, Linn County
Solar
400 MWIn study Linn, IAMISO Aug 2021target 2024
Battery storage project J2304, Columbia County
Battery storage
400 MWIn study Columbia, WIMISO Dec 2021target 2024
Solar + storage project J2302, St. Helena Parish County
Solar + storage
400 MWIn study St. Helena Parish, LAMISO Nov 2021target 2027
Solar + storage project J2173, Hinds County
Solar + storage
396 MWIn study Hinds, MSMISO Aug 2021target 2027
Solar + storage project J1946, Jasper County
Solar + storage
350 MWIn study Jasper, MSMISO Aug 2021target 2024
Solar project J2098, Calhoun County
Solar
309 MWIn study Calhoun, MIMISO Aug 2021target 2026
Solar + storage project J2205, Callaway County
Solar + storage
300 MWIn study Callaway, MOMISO Aug 2021target 2024
Wind + storage project J2128, Coles County
Wind + storage
300 MWIn study Coles, ILMISO Aug 2021target 2026
Solar project J2270, Sullivan County
Solar
300 MWIn study Sullivan, INMISO Aug 2021target 2024
Surplus; Pleasant Valley Peaker
Wind + storage
259 MWIn study MISO Aug 2021target 2023
Onshore wind project J2260, Presque Isle County
Onshore wind
252 MWIn study Presque Isle, MIMISO Oct 2021target 2023
Solar + storage project J2139, Livingston County
Solar + storage
250 MWIn study Livingston, MIMISO Sep 2021target 2024
Solar project J2143, Chicot County
Solar
250 MWIn study Chicot, ARMISO Oct 2021target 2027
Battery storage project J2100, Van Buren County
Battery storage
250 MWIn study Van Buren, MIMISO Aug 2021target 2024
Solar project J1872, Union County
Solar
250 MWIn study Union, ARMISO Aug 2021target 2028
Replace 250MW of the existing Petersburg coal unit with PV and DC-coupled battery storage; Petersburg 2
Solar + storage
250 MWIn study Pike, INMISO Oct 2021target 2024
Solar project J1873, Union County
Solar
250 MWIn study Union, ARMISO Aug 2021target 2028
Solar + storage project J2272, Clinton County
Solar + storage
250 MWIn study Clinton, IAMISO Jul 2021target 2026
Solar project J2294, Mississippi County
Solar
250 MWIn study Mississippi, ARMISO Aug 2021target 2028
Solar project J2149, Saline County
Solar
240 MWIn study Saline, ARMISO Nov 2021target 2024
Solar project J2317, Ouachita Parish County
Solar
225 MWIn study Ouachita Parish, LAMISO Dec 2021target 2027
Solar project J2001, Newaygo County
Solar
220 MWIn study Newaygo, MIMISO Aug 2021target 2025
Solar + storage project J1779, Dane County
Solar + storage
200 MWAgreement signed Dane, WIMISO Sep 2021target 2027
Onshore wind project J2080, Oliver County
Onshore wind
200 MWIn study Oliver, NDMISO Aug 2021target 2024
Solar project J1571, Lenawee County
Solar
200 MWAgreement signed Lenawee, MIMISO Dec 2021target 2025
Solar project J2061, Saginaw County
Solar
200 MWIn study Saginaw, MIMISO Aug 2021target 2024
Solar project J2289, Sunflower County
Solar
200 MWIn study Sunflower, MSMISO Sep 2021target 2028
Onshore wind project J1867, Franklin County
Onshore wind
200 MWIn study Franklin, IAMISO Nov 2021target 2025
Solar project J2089, Mississippi County
Solar
200 MWIn study Mississippi, ARMISO Nov 2021target 2027
Solar project J1603, Otsego County
Solar
200 MWAgreement signed Otsego, MIMISO Dec 2021target 2025
Solar project J1870, Tangipahoa Parish County
Solar
200 MWIn study Tangipahoa Parish, LAMISO Aug 2021target 2028
Onshore wind project J1701, Mcdonough County
Onshore wind
200 MWIn study Mcdonough, ILMISO Dec 2021target 2026
Onshore wind project J2250, Stutsman County
Onshore wind
200 MWIn study Stutsman, NDMISO Nov 2021target 2024
Solar project J2224, Iberville Parish County
Solar
200 MWIn study Iberville Parish, LAMISO Aug 2021target 2025
Solar project J1943, Columbia County
Solar
200 MWIn study Columbia, WIMISO Aug 2021target 2024
Solar + storage project J2153, Ashley County
Solar + storage
200 MWIn study Ashley, ARMISO Aug 2021target 2027
Battery storage project J1902, Wayne County
Battery storage
200 MWIn study Wayne, MIMISO Aug 2021target 2024
Solar project J2075, Liberty County
Solar
200 MWIn study Liberty, TXMISO Aug 2021target 2028
Solar project J2002, Washington County
Solar
200 MWIn study Washington, IAMISO Aug 2021target 2024
Solar + storage project J1891, Attala County
Solar + storage
200 MWIn study Attala, MSMISO Aug 2021target 2027
Solar project J2228, Concordia Parish County
Solar
200 MWIn study Concordia Parish, LAMISO Dec 2021target 2027
Battery storage project J1898, Olmsted County
Battery storage
200 MWIn study Olmsted, MNMISO Aug 2021target 2024
Solar project J1849, Hardin County
Solar
200 MWIn study Hardin, TXMISO Nov 2021target 2028
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)