United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in MISO (Midcontinent)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Other project G166, Sheboygan County Other |
2,400 MW | Withdrawn / abandoned |
| Onshore wind project J236, White County Onshore wind |
2,400 MW | Withdrawn / abandoned |
| Nuclear project J371, Ogle County Nuclear |
2,325 MW | Withdrawn / abandoned |
| Other project PQ0002, Cerro Gordo County Other |
2,000 MW | Withdrawn / abandoned |
| Onshore wind project G903, Wright County Onshore wind |
2,000 MW | Withdrawn / abandoned |
| Onshore wind project G705, Hand County Onshore wind |
2,000 MW | Withdrawn / abandoned |
| Other project J4176 Other |
1,750 MW | Withdrawn / abandoned |
| Nuclear project G733, Callaway County Nuclear |
1,650 MW | Withdrawn / abandoned |
| Gas project APP-100096 Gas |
1,640 MW | Withdrawn / abandoned |
| Gas project APP-100103 Gas |
1,640 MW | Withdrawn / abandoned |
| Nuclear project G867, Monroe County Nuclear |
1,563 MW | Withdrawn / abandoned |
| Gas project J4022, Ouachita Parish County Gas |
1,509 MW | Withdrawn / abandoned |
| Onshore wind project G897, Benton County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project G882, Dodge County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project G703, Hand County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project G883, Olmsted County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Other project IP05, Randolph County Other |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project G895, Scott County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project G902, Winnebago County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project G898, Benton County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project G896, Scott County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project G704, Hand County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project G884, Roberts County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Other project G265, Campbell County Other |
1,420 MW | Withdrawn / abandoned |
| Nuclear project J372, Rock Island County Nuclear |
1,373 MW | Withdrawn / abandoned |
| Gas project J4109, Iberville Parish County Gas |
1,300 MW | Withdrawn / abandoned |
| Coal project G484, Switzerland County Coal |
1,290 MW | Withdrawn / abandoned |
| Gas project J433, Union County Gas |
1,270 MW | Withdrawn / abandoned |
| Gas project J802, Vermillion County Gas |
1,244 MW | Withdrawn / abandoned |
| Gas project J480, Cherokee County Gas |
1,240 MW | Withdrawn / abandoned |
| Gas project J1848, Van Buren County Gas |
1,235 MW | Withdrawn / abandoned |
| Gas project J542, Vigo County Gas |
1,235 MW | Withdrawn / abandoned |
| Other project G493, Van Buren County Other |
1,221 MW | Withdrawn / abandoned |
| Gas project J812, Van Buren County Gas |
1,217 MW | Withdrawn / abandoned |
| Coal project G482, Ashtabula County Coal |
1,200 MW | Withdrawn / abandoned |
| Other project G167, Kenosha County Other |
1,200 MW | Withdrawn / abandoned |
| Gas project J434, Vermillion County Gas |
1,185 MW | Withdrawn / abandoned |
| Gas project J435, Eau Claire County Gas |
1,185 MW | Withdrawn / abandoned |
| Gas project J1130, Warren County Gas |
1,110 MW | Withdrawn / abandoned |
| Gas project G259, Dakota County Gas |
1,100 MW | Withdrawn / abandoned |
| Gas project J404, Jefferson Parish County Gas |
1,078 MW | Withdrawn / abandoned |
| Gas project J259, Shelby County Gas |
1,065 MW | Withdrawn / abandoned |
| Gas project G260, Goodhue County Gas |
1,061 MW | Withdrawn / abandoned |
| Gas project G065, St. Clair County Gas |
1,050 MW | Withdrawn / abandoned |
| Gas project G266, Scott County Gas |
1,005 MW | Withdrawn / abandoned |
| Onshore wind project G900, Wright County Onshore wind |
1,000 MW | Withdrawn / abandoned |
| Other project G108, Henderson County Other |
1,000 MW | Withdrawn / abandoned |
| Onshore wind project G899, Wright County Onshore wind |
1,000 MW | Withdrawn / abandoned |
| Other project G052, Sheboygan County Other |
1,000 MW | Withdrawn / abandoned |
| Onshore wind project J116, Hancock County Onshore wind |
999 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 Β· 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 Β· 638.1 GW
- MISO (Midcontinent)3,261 Β· 621.9 GW
- CAISO (California)2,186 Β· 619.9 GW
- Southeast (non-ISO utilities)2,738 Β· 603.3 GW
- SPP (Southwest Power Pool)1,846 Β· 382.9 GW
- NYISO (New York)1,531 Β· 324.1 GW
- ERCOT (Texas)1,158 Β· 262.0 GW
- ISO-NE (New England)982 Β· 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)