πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3,261621.9 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3,261 requests Β· page 1 of 66
ProjectCapacityStatusLocationRegionQueuedOnline
Other project G166, Sheboygan County
Other
2,400 MWWithdrawn / abandoned Sheboygan, WIMISO Aug 2000target 2007
Onshore wind project J236, White County
Onshore wind
2,400 MWWithdrawn / abandoned White, INMISO Dec 2011target 2018
Nuclear project J371, Ogle County
Nuclear
2,325 MWWithdrawn / abandoned Ogle, ILMISO Jun 2014target 2016
Other project PQ0002, Cerro Gordo County
Other
2,000 MWWithdrawn / abandoned Cerro Gordo, IAMISO Aug 2015target 2021
Onshore wind project G903, Wright County
Onshore wind
2,000 MWWithdrawn / abandoned Wright, MNMISO Oct 2007target 2010
Onshore wind project G705, Hand County
Onshore wind
2,000 MWWithdrawn / abandoned Hand, SDMISO Nov 2006target 2009
Other project J4176
Other
1,750 MWWithdrawn / abandoned MISO target 2028
Nuclear project G733, Callaway County
Nuclear
1,650 MWWithdrawn / abandoned Callaway, MOMISO Feb 2007target 2009
Gas project APP-100096
Gas
1,640 MWWithdrawn / abandoned LAMISO Aug 2025
Gas project APP-100103
Gas
1,640 MWWithdrawn / abandoned LAMISO Aug 2025
Nuclear project G867, Monroe County
Nuclear
1,563 MWWithdrawn / abandoned Monroe, MIMISO Sep 2007target 2010
Gas project J4022, Ouachita Parish County
Gas
1,509 MWWithdrawn / abandoned Ouachita Parish, LAMISO May 2025target 2030
Onshore wind project G897, Benton County
Onshore wind
1,500 MWWithdrawn / abandoned Benton, MNMISO Oct 2007target 2010
Onshore wind project G882, Dodge County
Onshore wind
1,500 MWWithdrawn / abandoned Dodge, MNMISO Oct 2007target 2010
Onshore wind project G703, Hand County
Onshore wind
1,500 MWWithdrawn / abandoned Hand, SDMISO Nov 2006target 2007
Onshore wind project G883, Olmsted County
Onshore wind
1,500 MWWithdrawn / abandoned Olmsted, MNMISO Oct 2007target 2011
Other project IP05, Randolph County
Other
1,500 MWWithdrawn / abandoned Randolph, ILMISO Dec 2001target 2010
Onshore wind project G895, Scott County
Onshore wind
1,500 MWWithdrawn / abandoned Scott, MNMISO Oct 2007target 2010
Onshore wind project G902, Winnebago County
Onshore wind
1,500 MWWithdrawn / abandoned Winnebago, ILMISO Oct 2007target 2012
Onshore wind project G898, Benton County
Onshore wind
1,500 MWWithdrawn / abandoned Benton, MNMISO Oct 2007target 2010
Onshore wind project G896, Scott County
Onshore wind
1,500 MWWithdrawn / abandoned Scott, MNMISO Oct 2007target 2010
Onshore wind project G704, Hand County
Onshore wind
1,500 MWWithdrawn / abandoned Hand, SDMISO Nov 2006target 2007
Onshore wind project G884, Roberts County
Onshore wind
1,500 MWWithdrawn / abandoned Roberts, SDMISO Oct 2007target 2011
Other project G265, Campbell County
Other
1,420 MWWithdrawn / abandoned Campbell, WYMISO Nov 2002target 2004
Nuclear project J372, Rock Island County
Nuclear
1,373 MWWithdrawn / abandoned Rock Island, ILMISO Jun 2014target 2019
Gas project J4109, Iberville Parish County
Gas
1,300 MWWithdrawn / abandoned Iberville Parish, LAMISO Oct 2025target 2030
Coal project G484, Switzerland County
Coal
1,290 MWWithdrawn / abandoned Switzerland, INMISO Nov 2004target 2004
Gas project J433, Union County
Gas
1,270 MWWithdrawn / abandoned Union, ARMISO Jan 2015
Gas project J802, Vermillion County
Gas
1,244 MWWithdrawn / abandoned Vermillion, INMISO Jun 2017target 2020
Gas project J480, Cherokee County
Gas
1,240 MWWithdrawn / abandoned Cherokee, TXMISO Sep 2015
Gas project J1848, Van Buren County
Gas
1,235 MWWithdrawn / abandoned Van Buren, MIMISO Aug 2021target 2023
Gas project J542, Vigo County
Gas
1,235 MWWithdrawn / abandoned Vigo, INMISO Jan 2016target 2020
Other project G493, Van Buren County
Other
1,221 MWWithdrawn / abandoned Van Buren, MIMISO Feb 2005target 2006
Gas project J812, Van Buren County
Gas
1,217 MWWithdrawn / abandoned Van Buren, MIMISO Jun 2017target 2017
Coal project G482, Ashtabula County
Coal
1,200 MWWithdrawn / abandoned Ashtabula, OHMISO Nov 2004target 2006
Other project G167, Kenosha County
Other
1,200 MWWithdrawn / abandoned Kenosha, WIMISO Aug 2000target 2008
Gas project J434, Vermillion County
Gas
1,185 MWWithdrawn / abandoned Vermillion, INMISO Mar 2015target 2019
Gas project J435, Eau Claire County
Gas
1,185 MWWithdrawn / abandoned Eau Claire, WIMISO Mar 2015target 2019
Gas project J1130, Warren County
Gas
1,110 MWWithdrawn / abandoned Warren, MSMISO Mar 2018target 2023
Gas project G259, Dakota County
Gas
1,100 MWWithdrawn / abandoned Dakota, MNMISO Oct 2002target 2005
Gas project J404, Jefferson Parish County
Gas
1,078 MWWithdrawn / abandoned Jefferson Parish, LAMISO Nov 2014target 2020
Gas project J259, Shelby County
Gas
1,065 MWWithdrawn / abandoned Shelby, INMISO Nov 2012target 2015
Gas project G260, Goodhue County
Gas
1,061 MWWithdrawn / abandoned Goodhue, MNMISO Oct 2002target 2004
Gas project G065, St. Clair County
Gas
1,050 MWWithdrawn / abandoned St. Clair, MIMISO Nov 2000target 2003
Gas project G266, Scott County
Gas
1,005 MWWithdrawn / abandoned Scott, MNMISO Nov 2002target 2005
Onshore wind project G900, Wright County
Onshore wind
1,000 MWWithdrawn / abandoned Wright, MNMISO Oct 2007target 2011
Other project G108, Henderson County
Other
1,000 MWWithdrawn / abandoned Henderson, KYMISO Jul 2001target 2004
Onshore wind project G899, Wright County
Onshore wind
1,000 MWWithdrawn / abandoned Wright, MNMISO Oct 2007target 2011
Other project G052, Sheboygan County
Other
1,000 MWWithdrawn / abandoned Sheboygan, WIMISO Aug 2000target 2004
Onshore wind project J116, Hancock County
Onshore wind
999 MWWithdrawn / abandoned Hancock, IAMISO Feb 2010target 2013
Page 1 of 66

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)