Gas project J259, Shelby County

Gas project J259, Shelby County is a 1,065 MW gas request withdrawn in the MISO interconnection queue, in Shelby County, Indiana.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2012 (completed)
  2. Withdrawn / abandonedJul 2014 (project stopped here)
  3. ConsentedJul 2014 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J259
Grid region
MISO (Midcontinent)
Connection point (POI)
Gwynneville 345 kV Substation
Location
Shelby County, Indiana
Technology
Gas: 1,065 MW
Total requested
1,065 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
6 November 2012
Agreement signed
8 July 2014
Proposed online date
April 2015
Withdrawn
July 2014

Location

Marker shows the centre of Shelby County; the queue data does not give exact sites.