United States βΊ Grid βΊ Interconnection queues βΊ Illinois
ONSHORE WIND Β· MISOOnshore wind project G902, Winnebago County
Onshore wind project G902, Winnebago County is a 1,500 MW onshore wind request withdrawn in the MISO interconnection queue, in Winnebago County, Illinois.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2007 (completed)
- Withdrawn / abandonedAug 2008 (project stopped here)
- ConsentedAug 2008 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G902
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Paddtown 345 kV Substation
- Location
- Winnebago County, Illinois
- Technology
- Wind: 1,500 MW
- Total requested
- 1,500 MW
- Study phase
- Feasibility
- Queue status
- Withdrawn
- Entered queue
- 23 October 2007
- Agreement signed
- 19 August 2008
- Proposed online date
- December 2012
- Withdrawn
- August 2008
Location
Marker shows the centre of Winnebago County; the queue data does not give exact sites.
Other requests in Winnebago County
- Solar project AH2-338, Winnebago CountySolar Β· 160 MW Β· in study
- Battery storage project AH1-564, Winnebago CountyBattery storage Β· 150 MW Β· in study
- Solar project AG2-516, Winnebago CountySolar Β· 120 MW Β· in study
- Rockford I Energy CenterGas Β· 40.0 MW Β· built
- Rockford II Energy CenterGas Β· 20.0 MW Β· built
- Rockford I Energy CenterGas Β· 20.0 MW Β· built
- Rockford II Energy CenterGas Β· 7.0 MW Β· built
- Rockford II Energy CenterGas Β· 6.0 MW Β· built
- Onshore wind project G901, Winnebago CountyOnshore wind Β· 600 MW Β· withdrawn
- Solar project AH1-234, Winnebago CountySolar Β· 224 MW Β· withdrawn
- Solar project AD2-102, Winnebago CountySolar Β· 200 MW Β· withdrawn
- Onshore wind project M09_CE28, Winnebago CountyOnshore wind Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem