Rockford I Energy Center is a 20.0 MW gas request built and operating in the PJM interconnection queue, in Winnebago County, Illinois, connecting to ComEd.
Request details
- Queue ID
- AC1-113
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Rockford
- Location
- Winnebago County, Illinois
- Technology
- Gas: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 27 October 2016
- Proposed online date
- December 2021
- Came online
- June 2021
Location
Marker shows the centre of Winnebago County; the queue data does not give exact sites.
Other requests in Winnebago County
- Solar project AH2-338, Winnebago CountySolar · 160 MW · in study
- Battery storage project AH1-564, Winnebago CountyBattery storage · 150 MW · in study
- Solar project AG2-516, Winnebago CountySolar · 120 MW · in study
- Rockford I Energy CenterGas · 40.0 MW · built
- Rockford II Energy CenterGas · 20.0 MW · built
- Rockford II Energy CenterGas · 7.0 MW · built
- Rockford II Energy CenterGas · 6.0 MW · built
- Onshore wind project G902, Winnebago CountyOnshore wind · 1,500 MW · withdrawn
- Onshore wind project G901, Winnebago CountyOnshore wind · 600 MW · withdrawn
- Solar project AH1-234, Winnebago CountySolar · 224 MW · withdrawn
- Solar project AD2-102, Winnebago CountySolar · 200 MW · withdrawn
- Onshore wind project M09_CE28, Winnebago CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem