United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in MISO (Midcontinent) (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9014.3 GW
Active in queue20.0 GW130 requests
Agreement signed14.3 GW90 requests
Withdrawn15321.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

90 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Other project J1490, Randolph County
Other
1,000 MWAgreement signed Randolph, MOMISO Apr 2019target 2024
Gas project J1246, Iberville Parish County
Gas
725 MWAgreement signed Iberville Parish, LAMISO Apr 2019target 2025
Other project J1488, Randolph County
Other
500 MWAgreement signed Randolph, MOMISO Apr 2019target 2024
Solar + storage project J1263, Clark County
Solar + storage
409 MWAgreement signed Clark, ILMISO Apr 2019target 2025
Onshore wind project J1360, Piatt County
Onshore wind
300 MWAgreement signed Piatt, ILMISO Apr 2019target 2024
Solar project J1214, Dane County
Solar
300 MWAgreement signed Dane, WIMISO Apr 2019target 2025
Solar project J1308, Posey County
Solar
300 MWAgreement signed Posey, INMISO Apr 2019target 2024
Onshore wind project MPC04000, Oliver County
Onshore wind
300 MWAgreement signed Oliver, NDMISO Apr 2019target 2023
Solar project J1216, Washington County
Solar
250 MWAgreement signed Washington, ILMISO Apr 2019target 2026
Onshore wind project J1432, Clinton County
Onshore wind
250 MWAgreement signed Clinton, IAMISO Apr 2019target 2025
Solar project J1466, Henderson County
Solar
250 MWAgreement signed Henderson, KYMISO Apr 2019target 2025
Onshore wind project MPC03800, Eddy County
Onshore wind
250 MWAgreement signed Eddy, NDMISO Feb 2019target 2027
Solar project J1415, Lonoke County
Solar
250 MWAgreement signed Lonoke, ARMISO Apr 2019target 2024
Onshore wind project J1289, Morgan County
Onshore wind
200 MWAgreement signed Morgan, ILMISO Apr 2019target 2024
Solar project J1481, Howard County
Solar
200 MWAgreement signed Howard, INMISO Apr 2019target 2025
Solar project J1196, Sanilac County
Solar
200 MWAgreement signed Sanilac, MIMISO Apr 2019target 2025
Solar project J1218, Muscatine County
Solar
200 MWAgreement signed Muscatine, IAMISO Apr 2019target 2026
Solar project J1241, Jefferson County
Solar
200 MWAgreement signed Jefferson, ILMISO Apr 2019target 2024
Solar project J1215, Arkansas County
Solar
200 MWAgreement signed Arkansas, ARMISO Apr 2019target 2024
Solar project J1379, Montcalm County
Solar
200 MWAgreement signed Montcalm, MIMISO Apr 2019target 2025
Solar project J1378, Fountain County
Solar
200 MWAgreement signed Fountain, INMISO Apr 2019target 2024
Solar project J1431, St. James Parish County
Solar
200 MWAgreement signed St. James Parish, LAMISO Apr 2019target 2024
Solar project J1190, Clinton County
Solar
200 MWAgreement signed Clinton, IAMISO Jan 2019target 2025
Solar project J1306, Perry County
Solar
200 MWAgreement signed Perry, ILMISO Apr 2019target 2024
Solar project J1381, Howard County
Solar
200 MWAgreement signed Howard, INMISO Apr 2019target 2026
Solar project J1348, Vermillion County
Solar
200 MWAgreement signed Vermillion, INMISO Apr 2019target 2025
Solar + storage project J1340, Jasper County
Solar + storage
200 MWAgreement signed Jasper, INMISO Apr 2019target 2025
Solar + storage project J1336, Jasper County
Solar + storage
200 MWAgreement signed Jasper, INMISO Apr 2019target 2025
Solar + storage project J1339, Jasper County
Solar + storage
200 MWAgreement signed Jasper, INMISO Apr 2019target 2025
Onshore wind project J1292, Ionia County
Onshore wind
198 MWAgreement signed Ionia, MIMISO Apr 2019target 2024
Battery storage project J1355, Laporte County
Battery storage
160 MWAgreement signed Laporte, INMISO Apr 2019target 2026
Onshore wind project MPC03900, Eddy County
Onshore wind
151 MWAgreement signed Eddy, NDMISO Apr 2019target 2027
Solar project J1482, White County
Solar
150 MWAgreement signed White, INMISO Apr 20192024
Solar project J1383, Fulton County
Solar
150 MWAgreement signed Fulton, ILMISO Apr 2019target 2025
Solar project J1465, Pointe Coupee Parish County
Solar
150 MWAgreement signed Pointe Coupee Parish, LAMISO Apr 2019target 2024
Solar project J1302, Saline County
Solar
150 MWAgreement signed Saline, ILMISO Apr 2019target 2025
Solar project J1382, Clark County
Solar
150 MWAgreement signed Clark, ILMISO Apr 2019target 2025
Solar project J1303, Jackson County
Solar
150 MWAgreement signed Jackson, ILMISO Apr 2019target 2026
Solar project J1268, Lincoln County
Solar
150 MWAgreement signed Lincoln, MOMISO Apr 2019target 2023
Solar + storage project J1422, Edwards County
Solar + storage
150 MWAgreement signed Edwards, ILMISO Apr 2019target 2024
Solar project J1311, St. Clair County
Solar
150 MWAgreement signed St. Clair, ILMISO Apr 2019target 2025
Solar project J1450, Webster County
Solar
150 MWAgreement signed Webster, KYMISO Apr 2019target 2025
Battery storage project J1357, Madison County
Battery storage
150 MWAgreement signed Madison, INMISO Apr 2019target 2025
Solar project J1320, Branch County
Solar
150 MWAgreement signed Branch, MIMISO Apr 2019target 2025
Solar project J1388, Gibson County
Solar
150 MWAgreement signed Gibson, INMISO Apr 2019target 2024
Battery storage project J1354, Decatur County
Battery storage
146 MWAgreement signed Decatur, INMISO Apr 2019target 2025
Solar project J1393, Pike County
Solar
130 MWAgreement signed Pike, INMISO Apr 2019target 2026
Battery storage project J1358, Laporte County
Battery storage
125 MWAgreement signed Laporte, INMISO Apr 2019target 2026
Solar project J1389, Saginaw County
Solar
120 MWAgreement signed Saginaw, MIMISO Apr 2019target 2025
Solar project J1234, Knox County
Solar
100 MWAgreement signed Knox, INMISO Apr 2019target 2023
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)