United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Texas, MISO

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown276,659 MW
Active in queue6,659 MW27 requests
Agreement signed332 MW3 requests
Withdrawn7015.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

27 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Replace 1163.3 MW of Sabine Units 3, 4 & 1 with 2 on 1 Combined Cycle Gas Turbine facility; Sabine 1
Gas
1,166 MWIn study Orange, TXMISO Aug 2020target 2026
Gas project E0030, Jefferson County
Gas Β· Entergy Texas, Inc.
820 MWIn study Jefferson, TXMISO Aug 2025target 2027
Gas project E0032, San Jacinto County
Gas Β· Entergy Texas, Inc.
478 MWIn study San Jacinto, TXMISO Aug 2025target 2027
Solar project J3045, Orange County
Solar
300 MWIn study Orange, TXMISO Sep 2022target 2026
Onshore wind project J3902, Jefferson County
Onshore wind
289 MWIn study Jefferson, TXMISO Feb 2025target 2028
Solar project J3986, Liberty County
Solar
270 MWIn study Liberty, TXMISO Oct 2024target 2030
Solar + storage project J3985, Polk County
Solar + storage
240 MWIn study Polk, TXMISO Nov 2024target 2030
Solar + storage project J3586, Montgomery County
Solar + storage
206 MWIn study Montgomery, TXMISO Apr 2024target 2028
Solar project J1760, Liberty County
Solar
205 MWAgreement signed Liberty, TXMISO Jun 2020target 2023
Battery storage project J3169, Hardin County
Battery storage
200 MWIn study Hardin, TXMISO Sep 2022target 2026
Solar project J2075, Liberty County
Solar
200 MWIn study Liberty, TXMISO Aug 2021target 2028
Solar project J1849, Hardin County
Solar
200 MWIn study Hardin, TXMISO Nov 2021target 2028
Solar project J2071, Hardin County
Solar
198 MWIn study Hardin, TXMISO Sep 2021target 2028
Solar + storage project J2689, Liberty County
Solar + storage
180 MWIn study Liberty, TXMISO Jul 2025target 2026
Solar project J2629, Newton County
Solar
175 MWIn study Newton, TXMISO Sep 2022target 2026
Solar project J2754, Polk County
Solar
170 MWIn study Polk, TXMISO Sep 2022target 2026
Solar project J1442, Polk County
Solar
165 MWUnder construction Polk, TXMISO Apr 2019target 2025
Solar project J1671, Walker County
Solar
150 MWUnder construction Walker, TXMISO Jun 2020target 2025
Battery storage project J4103, Trinity County
Battery storage
150 MWIn study Trinity, TXMISO Oct 2025target 2029
Solar + storage project J2897, San Jacinto County
Solar + storage
150 MWIn study San Jacinto, TXMISO Sep 2022target 2025
Solar project J2314, Liberty County
Solar
150 MWIn study Liberty, TXMISO Sep 2021target 2023
Solar project J2165, Liberty County
Solar
145 MWIn study Liberty, TXMISO Nov 2021target 2027
Gas project J1834, Orange County
Gas
126 MWIn study Orange, TXMISO Dec 2021target 2025
Solar project J2952, Chambers County
Solar
100 MWIn study Chambers, TXMISO Sep 2022target 2026
Solar project J483, Liberty County
Solar
100 MWAgreement signed Liberty, TXMISO Sep 20152024
Solar project J4124, Trinity County
Solar
100 MWIn study Trinity, TXMISO Aug 2025target 2029
Hydro project E291
Hydro
27.0 MWAgreement signed TXMISO May 20122020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)