Battery storage project J4103, Trinity County

Battery storage project J4103, Trinity County is a 150 MW battery storage request in interconnection study in the MISO interconnection queue, in Trinity County, Texas, connecting to EAST TEXAS ELECTRIC COOPERATIVE, INC..

Queue statusIn planning
  1. PlanningQueued Oct 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J4103
Grid region
MISO (Midcontinent)
Utility / transmission owner
EAST TEXAS ELECTRIC COOPERATIVE, INC.
Connection point (POI)
ONALASKA
Location
Trinity County, Texas
Technology
Battery: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
6 October 2025
Proposed online date
June 2029

Location

Marker shows the centre of Trinity County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Trinity County