United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in MISO (Midcontinent) (2022 requests) β€” page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown43582.2 GW
Active in queue82.2 GW435 requests
Agreement signed881 MW6 requests
Withdrawn56794.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

435 requests Β· page 9 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J3213, Hennepin County
Gas
51.0 MWIn study Hennepin, MNMISO Sep 2022target 2026
Surplus; J1369
Other
50.0 MWAgreement signed Dubois, INMISO May 2022target 2022
Surplus; J1002
Other
50.0 MWIn study Waushara, WIMISO May 2022target 2023
Solar project J2429, Dane County
Solar
50.0 MWIn study Dane, WIMISO Sep 2022target 2027
Solar project J3066, Osceola County
Solar
50.0 MWIn study Osceola, MIMISO Sep 2022target 2026
Solar project J2867, Wabasha County
Solar
50.0 MWIn study Wabasha, MNMISO Sep 2022target 2029
Battery storage project J3140, Porter County
Battery storage
50.0 MWIn study Porter, INMISO Sep 2022target 2026
Battery storage project J2045, Newton County
Battery storage
50.0 MWIn study Newton, INMISO Mar 2022target 2024
Surplus; J1386
Other
50.0 MWIn study Lake, INMISO May 2022target 2028
Battery storage project J2974, Adams County
Battery storage
50.0 MWIn study Adams, ILMISO Sep 2022target 2026
Surplus; Gratiot Solar
Other
50.0 MWIn study MISO Apr 2022target 2023
Solar + storage project J2951, Union County
Solar + storage
50.0 MWIn study Union, IAMISO Sep 2022target 2024
Surplus; Merricourt Solar
Other
49.9 MWIn study MISO Mar 2022target 2028
Solar project J2868, Jackson County
Solar
46.2 MWIn study Jackson, WIMISO Sep 2022target 2026
Battery storage project J1882, Tazewell County
Battery storage
45.0 MWIn study Tazewell, ILMISO Mar 2022target 2024
Battery storage project J1861, Laporte County
Battery storage
45.0 MWIn study Laporte, INMISO Mar 2022target 2024
Solar project J2756, Livingston County
Solar
42.0 MWIn study Livingston, KYMISO Sep 2022target 2025
Battery storage project J2457, Orleans Parish County
Battery storage
40.0 MWIn study Orleans Parish, LAMISO Sep 2022target 2025
Other project J2276, Douglas County
Other
39.5 MWIn study Douglas, MNMISO Apr 2022target 2022
Battery storage project J2404, East Baton Rouge Parish County
Battery storage
38.8 MWIn study East Baton Rouge Parish, LAMISO Sep 2022target 2025
Replacing 37 MW of natural gas generation with BESS at Joppa; Joppa
Other
37.0 MWIn study MISO Dec 2022target 2024
Solar project J3188, Marshall County
Solar
35.0 MWIn study Marshall, ILMISO Sep 2022target 2023
Solar project J2982, Warren County
Solar
35.0 MWIn study Warren, ILMISO Sep 2022target 2023
Surplus; J1304
Other
33.0 MWIn study Rock, WIMISO Aug 2022target 2023
Solar project J2908, Morgan County
Solar
30.0 MWIn study Morgan, ILMISO Jul 20222023
Surplus; J1188
Other
25.0 MWIn study Rock, WIMISO May 2022target 2022
Surplus; J1000
Other
25.0 MWIn study Grant, WIMISO May 2022target 2023
Surplus; J1305
Other
25.0 MWIn study Green, WIMISO Aug 2022target 2023
Surplus; J864
Other
25.0 MWIn study MISO Apr 2022target 2022
Solar project J3065, Oceana County
Solar
20.0 MWIn study Oceana, MIMISO Sep 2022target 2025
Gas project J2969, Kalkaska County
Gas
13.4 MWIn study Kalkaska, MIMISO Sep 2022target 2002
Solar project J3208, Dubois County
Solar
10.0 MWIn study Dubois, INMISO Sep 2022target 2023
Hydro project J1826, Dakota County
Hydro
4.0 MWIn study Dakota, MNMISO Sep 2022target 2024
Surplus; Petersburg
Other
3.0 MWIn study Pike, INMISO May 2022target 2023
Hydro project J3219, Dakota County
Hydro
3.0 MWIn study Dakota, MNMISO Sep 2022target 2023
Page 9 of 9

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)