United States › Grid › Interconnection queues › Louisiana
BATTERY STORAGE · MISOBattery storage project J2404, East Baton Rouge Parish County
Battery storage project J2404, East Baton Rouge Parish County is a 38.8 MW battery storage request in interconnection study in the MISO interconnection queue, in East Baton Rouge Parish County, Louisiana.
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2404
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- EAST
- Location
- East Baton Rouge Parish County, Louisiana
- Technology
- Battery: 38.8 MW
- Total requested
- 38.8 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- November 2025
Location
Marker shows the centre of East Baton Rouge Parish County; the queue data does not give exact sites.
Other requests in East Baton Rouge Parish County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem