United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2021 requests) โ€” page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,149339.1 GW
Active in queue227.7 GW896 requests
Agreement signed73.3 GW270 requests
Withdrawn2,149339.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,149 requests ยท page 7 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 177046, Duplin County
Solar ยท Masked
275 MWWithdrawn / abandoned Duplin, NCSoutheast May 2021
Solar project 170274, Richmond County
Solar ยท Masked
275 MWWithdrawn / abandoned Richmond, NCSoutheast Apr 2021
Battery storage project AG2-207, Anne Arundel County
Battery storage
275 MWWithdrawn / abandoned Anne Arundel, MDPJM Mar 2021target 2023
Solar project AG2-635, Brunswick County
Solar
270 MWWithdrawn / abandoned Brunswick, VAPJM Mar 2021target 2025
Four Creeks Energy Storage
Battery storage
261 MWWithdrawn / abandoned Tulare, CACAISO Apr 2021target 2030
Hub City Energy Storage
Battery storage
261 MWWithdrawn / abandoned Riverside, CACAISO Apr 2021target 2031
West Hills Energy Storage
Battery storage
261 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2025
Solar + storage project J2020, Beauregard Parish County
Solar + storage
260 MWWithdrawn / abandoned Beauregard Parish, LAMISO Aug 2021target 2024
Solar project J1868, Winn Parish County
Solar
260 MWWithdrawn / abandoned Winn Parish, LAMISO Aug 2021target 2024
Alviso Energy Storage
Battery storage
256 MWWithdrawn / abandoned Santa Clara, CACAISO Apr 2021target 2032
Maathai
Battery storage
256 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2033
Tres Rios Energy Center
Solar + storage
256 MWWithdrawn / abandoned Yuba, CACAISO Apr 2021target 2025
Gargantua Storage
Battery storage
253 MWWithdrawn / abandoned Riverside, CACAISO Apr 2021target 2024
Redonda Solar
Solar ยท J&R Power DevCo, LLC
253 MWWithdrawn / abandoned ERCOT Jan 2021target 2026
Risu
Battery storage
253 MWWithdrawn / abandoned Orange, CACAISO Apr 2021target 2030
Genoa Energy Storage
Battery storage
252 MWWithdrawn / abandoned Napa, CACAISO Apr 2021target 2031
Picador Energy Storage
Battery storage
252 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2032
Jaguar Energy Storage
Battery storage
252 MWWithdrawn / abandoned Alameda, CACAISO Apr 2021target 2034
Stony Creek Storage
Battery storage
252 MWWithdrawn / abandoned Tehama, CACAISO Apr 2021target 2031
Boxcar Solar 2
Solar ยท EDF Renewables Development, Inc.
251 MWWithdrawn / abandoned ERCOT Jul 2021target 2027
Solar + storage project Q426, Pinal County
Solar + storage
250 MWWithdrawn / abandoned Pinal, AZWest Sep 2021target 2025
Solar project AH1-625, Webster County
Solar
250 MWWithdrawn / abandoned Webster, WVPJM Sep 2021target 2025
Battery storage project Q429, Pinal County
Battery storage
250 MWWithdrawn / abandoned Pinal, AZWest Sep 2021target 2023
Solar + storage project GEN-2021-004, Carter County
Solar + storage
250 MWWithdrawn / abandoned Carter, OKSPP Apr 2021target 2027
Solar project IC-948, Mcduffie County
Solar
250 MWWithdrawn / abandoned Mcduffie, GASoutheast Apr 2021
Armstrong Battery Storage
Battery storage ยท Armstrong Power, LLC
250 MWWithdrawn / abandoned Armstrong, PAPJM Sep 2021target 2025
Onshore wind project J1865, Hardin County
Onshore wind
250 MWWithdrawn / abandoned Hardin, IAMISO Aug 2021target 2024
Battery storage project 102, Pima County
Battery storage
250 MWWithdrawn / abandoned Pima, AZWest Oct 2021target 2024
Solar project J2028, Crittenden County
Solar
250 MWWithdrawn / abandoned Crittenden, ARMISO Aug 2021target 2024
Solar project J2164, Pike County
Solar
250 MWWithdrawn / abandoned Pike, INMISO Aug 2021target 2024
Solar project Q432, Pinal County
Solar
250 MWWithdrawn / abandoned Pinal, AZWest Sep 2021target 2024
Maplewood Energy Storage
Battery storage ยท ACE Development Company
250 MWWithdrawn / abandoned Albany, NYNYISO Aug 2021
Troy Battery Storage
Battery storage ยท Troy Energy, LLC
250 MWWithdrawn / abandoned Wood, OHPJM Sep 2021target 2025
Onshore wind project J1864, Cerro Gordo County
Onshore wind
250 MWWithdrawn / abandoned Cerro Gordo, IAMISO Aug 2021target 2024
Ironwood Battery Storage
Battery storage ยท Helix Ironwood, LLC
250 MWWithdrawn / abandoned Lebanon, PAPJM Sep 2021target 2025
Battery storage project AG2-357, Will County
Battery storage ยท Bluegill Energy Storage LLC
250 MWWithdrawn / abandoned Will, ILPJM Mar 2021target 2024
Solar + storage project 21-12151, Weld County
Solar + storage
250 MWWithdrawn / abandoned Weld, COWest Dec 2021target 2024
Springdale Battery Storage II
Battery storage ยท Springdale Energy, LLC
250 MWWithdrawn / abandoned Allegheny, PAPJM Sep 2021target 2025
Battery storage project 101, Pima County
Battery storage
250 MWWithdrawn / abandoned Pima, AZWest Oct 2021target 2024
Battery storage project LGE-GIS-2021-016, Jefferson County
Battery storage
250 MWWithdrawn / abandoned Jefferson, KYSoutheast Mar 2021target 2024
Solar + storage project Q386, Pinal County
Solar + storage
250 MWWithdrawn / abandoned Pinal, AZWest Mar 2021target 2025
Surplus; J1419
Other
250 MWWithdrawn / abandoned MISO Aug 2021target 2022
Battery storage project AH1-559, Will County
Battery storage
250 MWWithdrawn / abandoned Will, ILPJM Sep 2021target 2025
Onshore wind project J1989, Brown County
Onshore wind
250 MWWithdrawn / abandoned Brown, SDMISO Aug 2021target 2025
Doswell Limited Partnership
Battery storage ยท Doswell Limited Partnership
250 MWWithdrawn / abandoned Hanover, VAPJM Sep 2021target 2025
Battery storage project GI-2021-31, Morgan County
Battery storage
250 MWWithdrawn / abandoned Morgan, COWest Oct 2021target 2024
Onshore wind project J1990, Stutsman County
Onshore wind
250 MWWithdrawn / abandoned Stutsman, NDMISO Nov 2021target 2025
Battery storage project AG2-622, Hanover County
Battery storage
250 MWWithdrawn / abandoned Hanover, VAPJM Mar 2021target 2023
Battery storage project AG2-350, Isle Of Wight County
Battery storage
250 MWWithdrawn / abandoned Isle Of Wight, VAPJM Mar 2021target 2023
Onshore wind project GEN-2021-099, Ellis County
Onshore wind
250 MWWithdrawn / abandoned Ellis, OKSPP Apr 20212025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)