United States βΊ Grid βΊ Interconnection queues
OTHER Β· MISOSurplus; J1419
Surplus; J1419 is a 250 MW other request withdrawn in the MISO interconnection queue, connecting to DUKE ENERGY INDIANA.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2021 (completed)
- Withdrawn / abandonedApr 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- S1008
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- Line Tap between Edwardsport and Amo 345kV
- Technology
- Other: 250 MW Β· Battery
- Total requested
- 250 MW
- Queue status
- Withdrawn
- Entered queue
- 4 August 2021
- Proposed online date
- December 2022
- Withdrawn
- April 2025
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem