๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2018 requests) โ€” page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,424226.5 GW
Active in queue67.1 GW348 requests
Agreement signed32.4 GW175 requests
Withdrawn1,424226.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,424 requests ยท page 7 of 29
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project Q290, Maricopa County
Battery storage
200 MWWithdrawn / abandoned Maricopa, AZWest Sep 2018target 2021
Solar project 105, Dillon County
Solar
200 MWWithdrawn / abandoned Dillon, SCSoutheast May 2018target 2020
Cunningham Solar 2
Solar ยท Invenergy
200 MWWithdrawn / abandoned Lamar, TXERCOT Aug 2018target 2023
Solar project J988, Wayne County
Solar
200 MWWithdrawn / abandoned Wayne, MSMISO Mar 2018target 2022
Solar project 76, Grant County
Solar
200 MWWithdrawn / abandoned Grant, WAWest Nov 2018target 2020
Solar project J1152, Hancock County
Solar
200 MWWithdrawn / abandoned Hancock, INMISO Mar 2018target 2021
Black Diamond Energy Storage 2
Battery storage
200 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2018target 2021
Solar project GEN-2018-124, Parmer County
Solar
200 MWWithdrawn / abandoned Parmer, TXSPP Nov 2018target 2027
Solar project J1149, Yellow Medicine County
Solar
200 MWWithdrawn / abandoned Yellow Medicine, MNMISO Mar 2018target 2021
Solar project J997, Lamoure County
Solar
200 MWWithdrawn / abandoned Lamoure, NDMISO Mar 2018target 2020
Equinox Solar 1
Solar ยท Invenergy Solar Project Development LLC
200 MWWithdrawn / abandoned Starr, TXERCOT Dec 2018target 2028
Onshore wind project GI-63, Osage County
Onshore wind
200 MWWithdrawn / abandoned Osage, OKSoutheast Jan 2018target 2020
Solar + storage project Company IV, Lander County
Solar + storage
200 MWWithdrawn / abandoned Lander, NVWest Sep 2018target 2022
Onshore wind project J1021, Piatt County
Onshore wind
200 MWWithdrawn / abandoned Piatt, ILMISO Mar 2018target 2021
Battery Storage
Battery storage
200 MWWithdrawn / abandoned Windham, CTISO-NE Dec 2018target 2024
Solar project Q10, Pinal County
Solar
200 MWWithdrawn / abandoned Pinal, AZWest Sep 2018target 2022
Onshore wind project J1114, Plymouth County
Onshore wind
200 MWWithdrawn / abandoned Plymouth, IAMISO Mar 2018target 2021
Solar project IC-704, Lee County
Solar
200 MWWithdrawn / abandoned Lee, GASoutheast May 2018
Alwest
Gas
200 MWWithdrawn / abandoned Anderson, TXERCOT Jul 2018
Onshore wind project J1065, Gratiot County
Onshore wind
200 MWWithdrawn / abandoned Gratiot, MIMISO Mar 2018target 2020
Solar + storage project 63, Pima County
Solar + storage
200 MWWithdrawn / abandoned Pima, AZWest Sep 2018target 2021
Onshore wind project GI-2018-27, Kit Carson County
Onshore wind
200 MWWithdrawn / abandoned Kit Carson, COWest Aug 2018target 2020
Battery storage project GEN-2018-030, Prowers County
Battery storage
200 MWWithdrawn / abandoned Prowers, COSPP May 2018target 2026
Solar project GEN-2018-113, New Madrid County
Solar
200 MWWithdrawn / abandoned New Madrid, MOSPP Nov 2018target 2023
Thunder Creek
Onshore wind ยท Nextera
200 MWWithdrawn / abandoned Hardeman, TXERCOT Aug 2018target 2021
Solar project AE1-022, Fauquier County
Solar
200 MWWithdrawn / abandoned Fauquier, VAPJM May 2018target 2020
Solar project GEN-2018-076, Logan County
Solar
200 MWWithdrawn / abandoned Logan, OKSPP Oct 2018target 2021
Solar project J1099, Iberville Parish County
Solar
200 MWWithdrawn / abandoned Iberville Parish, LAMISO Mar 2018target 2021
Solar project AE1-217, Delaware County
Solar
200 MWWithdrawn / abandoned Delaware, INPJM Sep 2018target 2022
Onshore wind project J980, Christian County
Onshore wind
200 MWWithdrawn / abandoned Christian, ILMISO Mar 2018target 2021
Walstrom
Gas ยท Castleman Power
200 MWWithdrawn / abandoned Austin, TXERCOT Jul 2018target 2023
Solar project GEN-2018-080, Craig County
Solar
200 MWWithdrawn / abandoned Craig, OKSPP Nov 2018target 2023
Solar project J1170, Cass County
Solar
200 MWWithdrawn / abandoned Cass, NDMISO Mar 2018target 2021
Solar + storage project Q284, Maricopa County
Solar + storage
200 MWWithdrawn / abandoned Maricopa, AZWest Sep 2018target 2020
Solar project AD2-190, Fauquier County
Solar
200 MWWithdrawn / abandoned Fauquier, VAPJM Mar 2018target 2020
Solar + storage project Company JH, Washoe County
Solar + storage
200 MWWithdrawn / abandoned Washoe, NVWest Sep 2018target 2020
Solar project GEN-2018-094, New Madrid County
Solar
200 MWWithdrawn / abandoned New Madrid, MOSPP Nov 2018target 2023
Moorhen Energy Storage
Battery storage
200 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2018target 2022
Battery storage project 1038, Utah County
Battery storage
200 MWWithdrawn / abandoned Utah, UTWest Jun 2018target 2021
Solar project GI-2018-25, Pueblo County
Solar
200 MWWithdrawn / abandoned Pueblo, COWest Aug 2018target 2022
Solar + storage project Company 167, Clark County
Solar + storage
200 MWWithdrawn / abandoned Clark, NVWest Sep 2018target 2022
Solar project J1105, Dakota County
Solar
200 MWWithdrawn / abandoned Dakota, MNMISO Mar 2018target 2020
Solar + storage project 1092, Millard County
Solar + storage
200 MWWithdrawn / abandoned Millard, UTWest Dec 2018target 2020
Onshore wind project AD2-101, Will County
Onshore wind
200 MWWithdrawn / abandoned Will, ILPJM Mar 2018target 2021
Onshore wind project J981, Washington County
Onshore wind
200 MWWithdrawn / abandoned Washington, IAMISO Mar 2018target 2021
Solar project Company IC, Washoe County
Solar
200 MWWithdrawn / abandoned Washoe, NVWest Mar 2018target 2020
Solar project J1044, Walworth County
Solar
200 MWWithdrawn / abandoned Walworth, WIMISO Mar 2018target 2022
Solar project J991, Clay County
Solar
200 MWWithdrawn / abandoned Clay, ILMISO Mar 2018target 2023
Solar project TCS-05, Adams County
Solar
200 MWWithdrawn / abandoned Adams, WAWest Nov 2018target 2020
Cunningham Solar 3
Solar ยท Invenergy
200 MWWithdrawn / abandoned Lamar, TXERCOT Aug 2018target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)