OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in PJM (Mid-Atlantic, Midwest) — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown905105.4 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

905 requests · page 7 of 19
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AG2-550, Randolph County
Solar · Riverstart Solar Park VI LLC
100 MWIn study Randolph, INPJM Feb 2025target 2024
Solar project AH2-068, Wood County
Solar
100 MWIn study Wood, OHPJM Jan 2022target 2027
Battery storage project AH2-378, Prince George County
Battery storage
100 MWIn study Prince George, VAPJM Mar 2022target 2025
Clermont County Solar Project
Solar
100 MWPaused / redesign Clermont, OHPJM Mar 2019target 2025
Battery storage project AH2-120, Mchenry County
Battery storage
100 MWIn study Mchenry, ILPJM Feb 2022target 2028
Solar project AH1-664, Fleming County
Solar · Hummingbird Energy LLC
100 MWIn study Fleming, KYPJM Feb 2025
Nottingham Solar
Solar
100 MWPaused / redesign Harrison, OHPJM Mar 20192023
Steward Creek Solar
Solar · Steward Creek Solar, LLC
100 MWIn study Lee, ILPJM Mar 2020target 2023
Headwaters Wind Farm III
Onshore wind
100 MWPaused / redesign Randolph, INPJM Sep 2018target 2026
Solar project AH2-010, Logan County
Solar
100 MWIn study Logan, OHPJM Oct 2021target 2024
Solar + storage project AH2-418, Berrien County
Solar + storage
100 MWIn study Berrien, MIPJM Mar 2022target 2026
Solar + storage project AI1-081, Jay County
Solar + storage
100 MWIn study Jay, INPJM Jul 2022target 2026
Battery storage project AH2-269, Ocean County
Battery storage
100 MWIn study Ocean, NJPJM Mar 2022target 2026
Battery storage project AI2-039, Surry County
Battery storage
100 MWIn study Surry, VAPJM Feb 2023target 2026
Battery storage project AH2-233, Pulaski County
Battery storage
100 MWIn study Pulaski, INPJM Mar 2022target 2026
Riverstart Solar Park V
Solar
100 MWPaused / redesign Randolph, INPJM Mar 2019target 2026
Solar project AG2-114, Livingston County
Solar · CPV Prairie Dock Solar, LLC
100 MWIn study Livingston, ILPJM Feb 2025target 2024
Bakers Pond Solar
Solar
100 MWPaused / redesign Prince George, VAPJM Sep 2018target 2026
Yadkins Energy Center
Battery storage · Yadkins Energy Center, LLC
100 MWIn study City Of Chesapeake, VAPJM Mar 2019target 2021
Battery storage project AG2-248, Elkhart County
Battery storage · Amberjack Solar LLC
100 MWIn study Elkhart, INPJM Jan 2025target 2024
Battery storage project AH1-314, Pittsylvania County
Battery storage · Pittsylvania Energy Storage LLC
100 MWIn study Pittsylvania, VAPJM Feb 2025target 2025
Battery storage project AH2-123, Lee County
Battery storage
100 MWIn study Lee, ILPJM Feb 2022target 2028
Solar + storage project AI1-180
Solar + storage
100 MWIn study KYPJM Sep 2022target 2027
Battery storage project AG2-571, Brunswick County
Battery storage · Zeus Storage, LLC
100 MWIn study Brunswick, VAPJM Mar 2025target 2024
Solar + storage project AH1-535, Hawkins County
Solar + storage · Pecan Flats Energy, LLC
100 MWIn study Hawkins, TNPJM Mar 2025target 2025
Solar project AG2-151, Cumberland County
Solar · Cumberland Solar, LLC
100 MWIn study Cumberland, VAPJM Feb 2025target 2024
Solar project AG2-068, Brunswick County
Solar · Virginia Electric and Power Company
100 MWIn study Brunswick, VAPJM Feb 2025target 2025
Battery storage project AI1-102, City Of Suffolk County
Battery storage
100 MWIn study City Of Suffolk, VAPJM Aug 2022target 2029
Solar + storage project AH2-267, Clearfield County
Solar + storage
100 MWIn study Clearfield, PAPJM Mar 2022target 2025
Solar project AH2-405, Franklin County
Solar
100 MWIn study Franklin, PAPJM Mar 2022target 2026
Solar + storage project AI1-009, Rush County
Solar + storage
100 MWIn study Rush, INPJM Apr 2022target 2026
Solar project AI2-329, Madison County
Solar
100 MWIn study Madison, OHPJM Mar 2023target 2026
Madison Solar 1
Solar · AEUG Madison Solar, LLC
100 MWIn study Madison, KYPJM Mar 2019target 2021
Battery storage project AI1-089, City Of Suffolk County
Battery storage
100 MWIn study City Of Suffolk, VAPJM Jul 2022target 2025
Bedington Energy Facility
Solar
100 MWPaused / redesign Frederick, MDPJM Apr 2019target 2025
Solar + storage project AI1-179, Cambria County
Solar + storage
100 MWIn study Cambria, PAPJM Sep 2022target 2027
Battery storage project AH2-124, Lee County
Battery storage
100 MWIn study Lee, ILPJM Feb 2022target 2028
Grand Marsh Solar
Solar · Deriva Energy Solar, LLC
100 MWIn study Kankakee, ILPJM Mar 2020target 2023
Battery storage project AH2-122, Lee County
Battery storage
100 MWIn study Lee, ILPJM Feb 2022target 2028
Battery storage project AH2-217, Morrow County
Battery storage
100 MWIn study Morrow, OHPJM Mar 2022target 2026
Cartersville Solar
Solar
99.9 MWPaused / redesign Powhatan, VAPJM Mar 2017target 2026
Solar project AH2-078, Charlotte County
Solar
99.7 MWIn study Charlotte, VAPJM Jan 2022target 2025
Brandonville Solar
Solar
99.6 MWPaused / redesign Preston, WVPJM Sep 2018target 2026
Solar + storage project AH1-216, Isle Of Wight County
Solar + storage · Boykin Solar Center, LLC
99.0 MWIn study Isle Of Wight, VAPJM Feb 2025target 2025
Onshore wind project AI2-488, Lee County
Onshore wind
97.2 MWIn study Lee, ILPJM Mar 2023target 2026
Onshore wind project AI2-487, Bureau County
Onshore wind
97.2 MWIn study Bureau, ILPJM Mar 2023target 2026
Solar project AI1-038, Carbon County
Solar
95.8 MWIn study Carbon, PAPJM Apr 2022target 2024
Red Maple Solar
Solar · Red Maple Solar, LLC
95.1 MWIn study Dekalb, ILPJM Aug 2020target 2023
Solar project AH2-155, Fulton County
Solar
95.0 MWIn study Fulton, OHPJM Mar 2022target 2025
Solar + storage project AH1-541, Dewitt County
Solar + storage · Golden Harvest Energy, LLC
92.4 MWIn study Dewitt, ILPJM Feb 2025target 2025
Page 7 of 19

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)