United States › Grid › Interconnection queues › Oklahoma

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Oklahoma — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown467102.4 GW
Active in queue52.5 GW240 requests
Agreement signed14.4 GW82 requests
Withdrawn467102.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

467 requests · page 6 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2016-144, Texas County
Onshore wind
175 MWWithdrawn / abandoned Texas, OKSPP Nov 20162020
Battery storage project GEN-2023-168, Oklahoma County
Battery storage
175 MWWithdrawn / abandoned Oklahoma, OKSPP Oct 2023target 2028
Onshore wind project GEN-2016-143, Texas County
Onshore wind
175 MWWithdrawn / abandoned Texas, OKSPP Nov 20162020
Solar project GEN-2022-042, Carter County
Solar
174 MWWithdrawn / abandoned Carter, OKSPP Jun 20222025
Gas project GEN-2005-023, Tulsa County
Gas
172 MWWithdrawn / abandoned Tulsa, OKSPP Dec 2005target 2007
Solar project GEN-2022-231, Logan County
Solar
166 MWWithdrawn / abandoned Logan, OKSPP Feb 2023target 2028
Onshore wind project GEN-2009-004, Woodward County
Onshore wind
161 MWWithdrawn / abandoned Woodward, OKSPP Feb 2009target 2010
Onshore wind project GEN-2015-029, Dewey County
Onshore wind
161 MWWithdrawn / abandoned Dewey, OKSPP Mar 20152020
Onshore wind project GEN-2014-061, Blaine County
Onshore wind
161 MWWithdrawn / abandoned Blaine, OKSPP Sep 2014target 2016
Onshore wind project GEN-2007-006, Blaine County
Onshore wind
160 MWWithdrawn / abandoned Blaine, OKSPP Feb 2007target 2009
Solar + storage project GEN-2023-188, Cotton County
Solar + storage
160 MWWithdrawn / abandoned Cotton, OKSPP Oct 2023target 2027
Onshore wind project GEN-2002-011, Woodward County
Onshore wind
160 MWWithdrawn / abandoned Woodward, OKSPP Jul 2002target 2003
Battery storage project GEN-2023-SR10, Dewey County
Battery storage
160 MWWithdrawn / abandoned Dewey, OKSPP Feb 20232025
Wind + storage project GEN-2021-098, Dewey County
Wind + storage
160 MWWithdrawn / abandoned Dewey, OKSPP May 2021target 2026
Onshore wind project GEN-2016-072, Grant County
Onshore wind
156 MWWithdrawn / abandoned Grant, OKSPP Mar 2016target 2018
Onshore wind project GI-47, Osage County
Onshore wind
151 MWWithdrawn / abandoned Osage, OKSoutheast Jan 2012target 2014
Solar project GEN-2017-066, Caddo County
Solar
151 MWWithdrawn / abandoned Caddo, OKSPP May 2017target 2020
Onshore wind project GEN-2011-009, Washita County
Onshore wind
150 MWWithdrawn / abandoned Washita, OKSPP Mar 2011target 2013
Onshore wind project GEN-2024-390, Murray County
Onshore wind
150 MWWithdrawn / abandoned Murray, OKSPP Mar 2025target 2031
Solar + storage project GEN-2021-066, Pittsburg County
Solar + storage
150 MWWithdrawn / abandoned Pittsburg, OKSPP Apr 2021target 2026
Solar project GEN-2018-117, Roger Mills County
Solar
150 MWWithdrawn / abandoned Roger Mills, OKSPP Nov 2018target 2026
Onshore wind project GEN-2008-054, Woodward County
Onshore wind
150 MWWithdrawn / abandoned Woodward, OKSPP Jun 2008target 2011
Onshore wind project GEN-2008-078, Woodward County
Onshore wind
150 MWWithdrawn / abandoned Woodward, OKSPP Jul 2008target 2011
Solar + storage project GEN-2023-051, Canadian County
Solar + storage
150 MWWithdrawn / abandoned Canadian, OKSPP Oct 2023target 2028
Solar project GEN-2022-237, Pottawatomie County
Solar
150 MWWithdrawn / abandoned Pottawatomie, OKSPP Feb 2023target 2028
Onshore wind project GEN-2008-043, Garfield County
Onshore wind
150 MWWithdrawn / abandoned Garfield, OKSPP May 2008target 2011
Solar project GEN-2024-300, Tillman County
Solar
150 MWWithdrawn / abandoned Tillman, OKSPP Mar 2025target 2028
Solar project GEN-2019-061, Major County
Solar
150 MWWithdrawn / abandoned Major, OKSPP May 2019target 2022
Battery storage project GEN-2023-174, Garvin County
Battery storage
150 MWWithdrawn / abandoned Garvin, OKSPP Oct 2023target 2028
Solar project GEN-2023-150, Caddo County
Solar
150 MWWithdrawn / abandoned Caddo, OKSPP Oct 2023target 2027
Onshore wind project GEN-2008-039, Beckham County
Onshore wind
150 MWWithdrawn / abandoned Beckham, OKSPP May 2008target 2010
Onshore wind project GEN-2010-030, Major County
Onshore wind
150 MWWithdrawn / abandoned Major, OKSPP May 2010target 2014
Solar + storage project GEN-2023-136, Craig County
Solar + storage
150 MWWithdrawn / abandoned Craig, OKSPP Oct 2023target 2028
Onshore wind project GEN-2016-148, Kay County
Onshore wind
150 MWWithdrawn / abandoned Kay, OKSPP Nov 2016target 2019
Onshore wind project GEN-2002-006, Texas County
Onshore wind
150 MWWithdrawn / abandoned Texas, OKSPP Apr 2002target 2005
Battery storage project GEN-2022-091, Mccurtain County
Battery storage
150 MWWithdrawn / abandoned Mccurtain, OKSPP Nov 2022target 2026
Battery storage project GEN-2023-166, Oklahoma County
Battery storage
150 MWWithdrawn / abandoned Oklahoma, OKSPP Oct 2023target 2028
Onshore wind project GEN-2008-109, Texas County
Onshore wind
150 MWWithdrawn / abandoned Texas, OKSPP Sep 2008target 2011
Onshore wind project GEN-2005-006, Ellis County
Onshore wind
150 MWWithdrawn / abandoned Ellis, OKSPP Mar 2005target 2006
Solar project GEN-2022-090, Mccurtain County
Solar
150 MWWithdrawn / abandoned Mccurtain, OKSPP Nov 2022target 2026
Onshore wind project GEN-2005-009, Dewey County
Onshore wind
150 MWWithdrawn / abandoned Dewey, OKSPP Apr 2005target 2006
Solar project GEN-2022-166, Garvin County
Solar
150 MWWithdrawn / abandoned Garvin, OKSPP Feb 2023target 2028
Onshore wind project GEN-2004-021, Custer County
Onshore wind
150 MWWithdrawn / abandoned Custer, OKSPP Oct 2004target 2005
Solar project GEN-2021-091, Pontotoc County
Solar
150 MWWithdrawn / abandoned Pontotoc, OKSPP Apr 2021target 2027
Onshore wind project GEN-2007-032, Custer County
Onshore wind
150 MWWithdrawn / abandoned Custer, OKSPP Jul 2007target 2013
Onshore wind project GEN-2009-070, Beckham County
Onshore wind
150 MWWithdrawn / abandoned Beckham, OKSPP Dec 2009target 2011
Battery storage project GEN-2022-110, Coal County
Battery storage
150 MWWithdrawn / abandoned Coal, OKSPP Feb 2023target 2026
Solar project GEN-2015-067, Noble County
Solar
150 MWWithdrawn / abandoned Noble, OKSPP Oct 2015target 2017
Onshore wind project GEN-2014-026, Beaver County
Onshore wind
150 MWWithdrawn / abandoned Beaver, OKSPP Sep 2014target 2016
Solar + storage project GEN-2023-049, Mayes County
Solar + storage
150 MWWithdrawn / abandoned Mayes, OKSPP Oct 2023target 2028
Page 6 of 10

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)