United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
ONSHORE WIND Β· SPPOnshore wind project GEN-2010-030, Major County
Onshore wind project GEN-2010-030, Major County is a 150 MW onshore wind request withdrawn in the SPP interconnection queue, in Major County, Oklahoma, connecting to WFEC.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2010 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2010-030
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WFEC
- Connection point (POI)
- TAP MOORELAND βΓΓ¬ GLASS MOUNTAIN 138kV
- Location
- Major County, Oklahoma
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 24 May 2010
- Proposed online date
- March 2014
Location
Marker shows the centre of Major County; the queue data does not give exact sites.
Other requests in Major County
- Onshore wind project GEN-2015-048, Major CountyOnshore wind Β· 200 MW Β· built
- Solar project GEN-2019-061, Major CountySolar Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2016-107, Major CountyOnshore wind Β· 142 MW Β· withdrawn
- Battery storage project GEN-2022-064, Major CountyBattery storage Β· 80.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem