Solar project GEN-2018-117, Roger Mills County

Solar project GEN-2018-117, Roger Mills County is a 150 MW solar request withdrawn in the SPP interconnection queue, in Roger Mills County, Oklahoma, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2018 (completed)
  2. Withdrawn / abandonedJun 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2018-117
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Sweetwater 230kV
Location
Roger Mills County, Oklahoma
Technology
Solar: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
20 November 2018
Proposed online date
May 2026
Withdrawn
June 2023

Location

Marker shows the centre of Roger Mills County; the queue data does not give exact sites.