SOLAR Β· SPP

Solar project GEN-2022-237, Pottawatomie County

Solar project GEN-2022-237, Pottawatomie County is a 150 MW solar request withdrawn in the SPP interconnection queue, in Pottawatomie County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandonedMar 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-237
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Maud 138 kV substation
Location
Pottawatomie County, Oklahoma
Technology
Solar: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
28 February 2023
Proposed online date
September 2028
Withdrawn
March 2025

Location

Marker shows the centre of Pottawatomie County; the queue data does not give exact sites.