United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Gas interconnection queue in the USA — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown688263.4 GW
Active in queue263.4 GW688 requests
Agreement signed39.9 GW131 requests
Withdrawn2,231897.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

688 requests · page 5 of 14
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project ERAS-2025-010, Oklahoma County
Gas
496 MWIn study Oklahoma, OKSPP Sep 2025target 2029
Gas project GEN-2024-013, Mcclain County
Gas
496 MWIn study Mcclain, OKSPP Aug 2024target 2030
Black Mountain Somervell Gas Combined
Gas · Fort Worth Power Core LLC
495 MWIn study Somervell, TXERCOT Apr 2025target 2029
Gas project 977444, Anson County
Gas
495 MWIn study Anson, NCSoutheast Jun 2025
Gas project GEN-2024-321, Seminole County
Gas
493 MWIn study Seminole, OKSPP Mar 2025target 2030
Gas project GEN-2024-GR1, Oklahoma County
Gas
492 MWAgreement signed Oklahoma, OKSPP Jan 2024target 2026
Halyard Wharton
Gas · Halyard Energy
484 MWPaused / redesign Wharton, TXERCOT Mar 2014target 2021
Gas project GI-2006-1e, El Paso County
Gas
483 MWAgreement signed El Paso, COWest Jan 2006target 2007
North Royal Thermal (TEF- Due Diligence)
Gas · Invenergy Energy Transition Development LLC
479 MWIn study Lamar, TXERCOT Jun 2024target 2030
Gas project E0032, San Jacinto County
Gas · Entergy Texas, Inc.
478 MWIn study San Jacinto, TXMISO Aug 2025target 2027
Gas project GEN-2023-222, Gage County
Gas
478 MWIn study Gage, NESPP Oct 2023target 2030
Waterford 5
Gas · Entergy Louisiana, LLC
478 MWIn study St. Charles Parish, LAMISO Aug 2025target 2028
Gas project GEN-2023-224, Lancaster County
Gas
478 MWIn study Lancaster, NESPP Oct 2023target 2029
Gas project GEN-2024-343, Harrison County
Gas
471 MWIn study Harrison, TXSPP Mar 2025target 2030
Gas project J4021, Sullivan County
Gas
470 MWIn study Sullivan, INMISO May 2025target 2028
Gas project J3331, Sullivan County
Gas
470 MWIn study Sullivan, INMISO Apr 2024target 2028
Gregory Power Development SLF
Gas · Gregory Power Partners LLC
470 MWIn study San Patricio, TXERCOT Nov 2024target 2028
Gas project GI-129, Payne County
Gas
460 MWIn study Payne, OKSoutheast Jul 2025target 2030
Gas project GI-104, Payne County
Gas
460 MWAgreement signed Payne, OKSoutheast Jul 2022target 2026
Gas project GI-132, Butler County
Gas
460 MWIn study Butler, MOSoutheast Jul 2025target 2030
Gas project GI-130, Payne County
Gas
460 MWIn study Payne, OKSoutheast Jul 2025target 2030
Gas project GI-103, Creek County
Gas
460 MWAgreement signed Creek, OKSoutheast Jul 2022target 2027
Gas project GI-131, Randolph County
Gas
460 MWIn study Randolph, MOSoutheast Jul 2025target 2030
Gas project GI-126, Randolph County
Gas
460 MWIn study Randolph, MOSoutheast Jan 2025target 2029
Gas project GI-128, Clinton County
Gas
460 MWIn study Clinton, MOSoutheast Jul 2025target 2030
Gas project GI-121, Randolph County
Gas
460 MWAgreement signed Randolph, MOSoutheast May 2024target 2030
Gas project GI-101, Clinton County
Gas
460 MWAgreement signed Clinton, MOSoutheast Jul 2022target 2027
Gas project 301, Colleton County
Gas
458 MWIn study Colleton, SCSoutheast May 2025target 2032
Gas project 300, Colleton County
Gas
458 MWIn study Colleton, SCSoutheast May 2025target 2032
Gas project GEN-2024-247, Payne County
Gas
457 MWIn study Payne, OKSPP Mar 2025target 2030
NRG THW GT 345 (Tef)
Gas · NRG THW GT LLC
456 MWAgreement signed Harris, TXERCOT Nov 2022target 2026
Gas project 960889, Rowan County
Gas
455 MWIn study Rowan, NCSoutheast Jun 2024
Gas project 961188, Stokes County
Gas
455 MWIn study Stokes, NCSoutheast Jun 2024
Gas project 961210, Stokes County
Gas
455 MWIn study Stokes, NCSoutheast Jun 2024
Gas project 956747, Rowan County
Gas
455 MWIn study Rowan, SCSoutheast Jun 2024
Gas project E0037, Sheboygan County
Gas · Wisconsin Power and Light Company (WPL)
455 MWIn study Sheboygan, WIMISO Aug 2025target 2025
Gas project E0038, Winnebago County
Gas · Wisconsin Power and Light Company (WPL)
455 MWIn study Winnebago, WIMISO Aug 2025target 2025
TRIFECTA Gas
Gas · NET Power
453 MWIn study Midland, TXERCOT Jun 2023target 2030
Gas project 2023-G13, La Paz County
Gas
453 MWIn study La Paz, AZWest Oct 2023target 2027
Gas project ERAS-2025-007, Nodaway County
Gas
451 MWIn study Nodaway, MOSPP Oct 2025target 2030
Gas project ERAS-2025-013, Nodaway County
Gas
451 MWIn study Nodaway, MOSPP Sep 2025target 2030
Gas project 08-030, Morrow County
Gas
450 MWPaused / redesign Morrow, ORWest May 2008target 2013
Gas project 08-031, Columbia County
Gas
450 MWPaused / redesign Columbia, ORWest May 2008target 2014
Calpine Guadalupe Peakers
Gas · Guadalupe Peaking Energy Center, LLC
450 MWIn study Guadalupe, TXERCOT Nov 2021target 2027
Big Watt Power Austin-1
Gas · Big Watt Power Austin-1 LLC
449 MWIn study Caldwell, TXERCOT Oct 2025target 2028
NRG Greens Bayou 6 (TEF-Due Diligence)
Gas · NRG Greens Bayou 6 LLC
445 MWAgreement signed Harris, TXERCOT Aug 2022target 2028
Vast Sands Power II (TEF-Due Diligence)
Gas · Permian Power I LLC
440 MWAgreement signed Ward, TXERCOT Jul 2024target 2028
Vast Sands Power I (TEF -Due Diligence)
Gas · Permian Power I LLC
440 MWAgreement signed Ward, TXERCOT Jul 2024target 2028
Cannon Falls Uprate
Gas · Invenergy Cannon Falls, LLC
428 MWIn study Goodhue, MNMISO Aug 2025target 2028
Gas project Q40, Maricopa County
Gas
425 MWIn study Maricopa, AZWest Aug 2023target 2028
Page 5 of 14

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)