Requests shown579114.4 GW
Active in queue59.6 GW300 requests
Agreement signed11.2 GW69 requests
Withdrawn579114.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

579 requests · page 5 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project J3557, Morgan County
Battery storage
200 MWWithdrawn / abandoned Morgan, INMISO Apr 2024target 2028
Solar project AG2-165, Marshall County
Solar · Wahoo Solar LLC
200 MWWithdrawn / abandoned Marshall, INPJM Feb 2025target 2024
Solar project J2664, Montgomery County
Solar
200 MWWithdrawn / abandoned Montgomery, INMISO Sep 2022target 2026
Solar project J2805, Fountain County
Solar
200 MWWithdrawn / abandoned Fountain, INMISO Sep 2022target 2026
Onshore wind project AC2-080, Jasper County
Onshore wind
200 MWWithdrawn / abandoned Jasper, INPJM Feb 2017target 2019
Onshore wind project G998, Clinton County
Onshore wind
200 MWWithdrawn / abandoned Clinton, INMISO Apr 2008target 2010
Solar project J1074, Gibson County
Solar
200 MWWithdrawn / abandoned Gibson, INMISO Mar 2018target 2022
Solar project J3294, Daviess County
Solar
200 MWWithdrawn / abandoned Daviess, INMISO Apr 2024target 2027
Solar project J1606, Fountain County
Solar
200 MWWithdrawn / abandoned Fountain, INMISO Jun 2020target 2023
Solar project AH1-653, Howard County
Solar
200 MWWithdrawn / abandoned Howard, INPJM Sep 2021target 2025
Onshore wind project AD2-132, Pulaski County
Onshore wind
200 MWWithdrawn / abandoned Pulaski, INPJM Mar 2018target 2020
Solar project J1548, Putnam County
Solar
200 MWWithdrawn / abandoned Putnam, INMISO Jun 2020target 2024
Solar project J1662, Newton County
Solar
200 MWWithdrawn / abandoned Newton, INMISO Jun 2020target 2023
Solar project J1768, Orange County
Solar
200 MWWithdrawn / abandoned Orange, INMISO Jun 2020target 2023
Battery storage project LGE-GIS-2021-024, Floyd County
Battery storage
200 MWWithdrawn / abandoned Floyd, INSoutheast Oct 2021target 2024
Onshore wind project G864, White County
Onshore wind
200 MWWithdrawn / abandoned White, INMISO Sep 2007target 2013
Onshore wind project J1966, Clinton County
Onshore wind
200 MWWithdrawn / abandoned Clinton, INMISO Mar 2022target 2025
Onshore wind project AB2-028, Henry County
Onshore wind
200 MWWithdrawn / abandoned Henry, INPJM Feb 2016target 2018
Onshore wind project J1627, White County
Onshore wind
200 MWWithdrawn / abandoned White, INMISO Jun 2020target 2022
Onshore wind project AD2-138, Warren County
Onshore wind
200 MWWithdrawn / abandoned Warren, INPJM Mar 2018target 2020
Onshore wind project H002, Clinton County
Onshore wind
200 MWWithdrawn / abandoned Clinton, INMISO Jul 2009target 2009
Onshore wind project J083, Warren County
Onshore wind
200 MWWithdrawn / abandoned Warren, INMISO Oct 2009target 2012
Solar project J3414, Posey County
Solar
200 MWWithdrawn / abandoned Posey, INMISO Apr 2024target 2028
Solar project AF1-298, Delaware County
Solar
200 MWWithdrawn / abandoned Delaware, INPJM Sep 2019target 2023
Onshore wind project G835, Clinton County
Onshore wind
200 MWWithdrawn / abandoned Clinton, INMISO Aug 2007target 2011
Solar project J1593, Rush County
Solar
200 MWWithdrawn / abandoned Rush, INMISO Jun 2020target 2024
Onshore wind project H015, Boone County
Onshore wind
200 MWWithdrawn / abandoned Boone, INMISO Apr 2008target 2009
Solar project J3997, Pike County
Solar
200 MWWithdrawn / abandoned Pike, INMISO May 2025target 2028
Solar project J1565, Lawrence County
Solar
200 MWWithdrawn / abandoned Lawrence, INMISO Jun 2020target 2023
Solar project J2046, Wabash County
Solar
200 MWWithdrawn / abandoned Wabash, INMISO Aug 2021target 2024
Onshore wind project J1835, Spencer County
Onshore wind
200 MWWithdrawn / abandoned Spencer, INMISO Jun 2020target 2023
Solar project J2407, Sullivan County
Solar
198 MWWithdrawn / abandoned Sullivan, INMISO Sep 2022target 2027
Onshore wind project J054, Tipton County
Onshore wind
198 MWWithdrawn / abandoned Tipton, INMISO Jan 2013target 2011
Onshore wind project J270, Newton County
Onshore wind
198 MWWithdrawn / abandoned Newton, INMISO Mar 2013target 2018
Gas project J2144, Jasper County
Gas
195 MWWithdrawn / abandoned Jasper, INMISO Sep 2021target 2024
Solar project J3257, Pulaski County
Solar
190 MWWithdrawn / abandoned Pulaski, INMISO Apr 2024target 2026
Battery storage project J2766, Howard County
Battery storage
190 MWWithdrawn / abandoned Howard, INMISO Aug 2023target 2025
Onshore wind project J156, Marshall County
Onshore wind
186 MWWithdrawn / abandoned Marshall, INMISO Jun 2010
Solar project AH1-291, Huntington County
Solar · Invenergy Solar Project Development LLC
185 MWWithdrawn / abandoned Huntington, INPJM Sep 2021target 2025
Solar project AG2-576, Dekalb County
Solar
180 MWWithdrawn / abandoned Dekalb, INPJM Mar 2021target 2024
Solar project AH1-549, Allen County
Solar · Leeward Renewable Energy Development, LLC
180 MWWithdrawn / abandoned Allen, INPJM Sep 2021target 2025
Solar project J2130, Vermillion County
Solar
180 MWWithdrawn / abandoned Vermillion, INMISO Mar 2022target 2024
Solar project J1815, Montgomery County
Solar
180 MWWithdrawn / abandoned Montgomery, INMISO Mar 2022target 2023
Solar project J1829, Shelby County
Solar
180 MWWithdrawn / abandoned Shelby, INMISO Jun 2020target 2024
Solar project AF1-221, Franklin County
Solar · Yellow Perch Solar LLC
180 MWWithdrawn / abandoned Franklin, INPJM Sep 2019target 2022
Onshore wind project J564, Fayette County
Onshore wind
176 MWWithdrawn / abandoned Fayette, INMISO May 2016target 2018
Solar project J3494, Greene County
Solar
175 MWWithdrawn / abandoned Greene, INMISO Apr 2024target 2028
Solar project J642, Montgomery County
Solar
175 MWWithdrawn / abandoned Montgomery, INMISO May 2016target 2020
Onshore wind project AA2-148, Fayette County
Onshore wind
174 MWWithdrawn / abandoned Fayette, INPJM Apr 2015target 2017
Solar project J2512, Kosciusko County
Solar
173 MWWithdrawn / abandoned Kosciusko, INMISO Sep 2022target 2025
Page 5 of 12

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)