πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

ONSHORE WIND Β· PJM

Onshore wind project AA2-148, Fayette County

Onshore wind project AA2-148, Fayette County is a 174 MW onshore wind request withdrawn in the PJM interconnection queue, in Fayette County, Indiana, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2015 (completed)
  2. Withdrawn / abandonedApr 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AA2-148
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Madison-Tanners Creek 138kV
Location
Fayette County, Indiana
Technology
Wind: 174 MW
Total requested
174 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Withdrawn
Entered queue
30 April 2015
Proposed online date
December 2017
Withdrawn
April 2021

Location

Marker shows the centre of Fayette County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Fayette County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem