United States βΊ Grid βΊ Interconnection queues βΊ Indiana
ONSHORE WIND Β· PJMOnshore wind project AA2-148, Fayette County
Onshore wind project AA2-148, Fayette County is a 174 MW onshore wind request withdrawn in the PJM interconnection queue, in Fayette County, Indiana, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2015 (completed)
- Withdrawn / abandonedApr 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AA2-148
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Madison-Tanners Creek 138kV
- Location
- Fayette County, Indiana
- Technology
- Wind: 174 MW
- Total requested
- 174 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 30 April 2015
- Proposed online date
- December 2017
- Withdrawn
- April 2021
Location
Marker shows the centre of Fayette County; the queue data does not give exact sites.
Other requests in Fayette County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem