United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

SOLAR Β· MISO

Solar project J642, Montgomery County

Solar project J642, Montgomery County is a 175 MW solar request withdrawn in the MISO interconnection queue, in Montgomery County, Indiana.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedJun 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J642
Grid region
MISO (Midcontinent)
Connection point (POI)
Whitesville Sub 230kV
Location
Montgomery County, Indiana
Technology
Solar: 175 MW
Total requested
175 MW
Study phase
GIA
Queue status
Withdrawn
Entered queue
9 May 2016
Proposed online date
April 2020
Withdrawn
June 2017

Location

Marker shows the centre of Montgomery County; the queue data does not give exact sites.

Power plants in Indiana Β· Transmission lines in Indiana

Other requests in Montgomery County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem