Requests shown26871.3 GW
Active in queue71.3 GW268 requests
Agreement signed0.0 MW0 requests
Withdrawn9926.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

268 requests Β· page 5 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2024-210, Cheyenne County
Solar
150 MWIn study Cheyenne, KSSPP Mar 2025target 2028
Battery storage project GEN-2024-306, Lea County
Battery storage
150 MWIn study Lea, NMSPP Mar 2025target 2031
Solar + storage project ERAS-2025-032, Stafford County
Solar + storage
150 MWIn study Stafford, KSSPP Oct 2025target 2029
Solar + storage project ERAS-2025-033, Ford County
Solar + storage
150 MWIn study Ford, KSSPP Oct 2025target 2027
Solar + storage project ERAS-2025-005, Yell County
Solar + storage
150 MWIn study Yell, ARSPP Sep 2025target 2029
Battery storage project GEN-2024-332, Oklahoma County
Battery storage
150 MWIn study Oklahoma, OKSPP Mar 2025target 2027
Solar project GEN-2024-283, Meade County
Solar
150 MWIn study Meade, SDSPP Mar 2025target 2030
Battery storage project GEN-2025-SR4, Edwards County
Battery storage
150 MWIn study Edwards, KSSPP Aug 2025target 2028
Solar project GEN-2024-282, Meade County
Solar
150 MWIn study Meade, SDSPP Mar 2025target 2030
Solar + storage project GEN-2024-117, Washington County
Solar + storage
150 MWIn study Washington, OKSPP Mar 2025target 2028
Other project ERAS-2025-031, Wyandotte County
Other
150 MWIn study Wyandotte, KSSPP Oct 2025target 2028
Battery storage project GEN-2025-SR3, Clark County
Battery storage
150 MWIn study Clark, KSSPP Aug 2025target 2028
Battery storage project GEN-2024-277, Shawnee County
Battery storage
150 MWIn study Shawnee, KSSPP Mar 2025target 2030
Solar project GEN-2024-376, Sabine County
Solar
142 MWIn study Sabine, TXSPP Mar 2025target 2028
Battery storage project ERAS-2025-036, Potter County
Battery storage
140 MWIn study Potter, TXSPP Oct 2025target 2029
Solar + storage project GEN-2024-362, Grady County
Solar + storage
140 MWIn study Grady, OKSPP Mar 2025target 2029
Solar project GEN-2024-157, Kiowa County
Solar
140 MWIn study Kiowa, OKSPP Mar 2025target 2029
Gas project ERAS-2025-035, Brown County
Gas
138 MWIn study Brown, SDSPP Oct 2025target 2029
Gas project GEN-2024-286, Le Flore County
Gas
136 MWIn study Le Flore, OKSPP Mar 2025target 2031
Battery storage project GEN-2026-PR4, Hansford County
Battery storage
132 MWIn study Hansford, TXSPP Dec 2025
Solar project GEN-2024-288, Cloud County
Solar
130 MWIn study Cloud, KSSPP Mar 2025target 2030
Other project GEN-2025-SR13, Seminole County
Other
130 MWIn study Seminole, OKSPP May 2025target 2029
Other project GEN-2025-SR15, Mcclain County
Other
125 MWIn study Mcclain, OKSPP May 2025target 2029
Battery storage project GEN-2024-251, Eddy County
Battery storage
125 MWIn study Eddy, NMSPP Mar 2025target 2029
Gas project GEN-2024-334, Kay County
Gas
124 MWIn study Kay, OKSPP Mar 2025target 2029
Battery storage project ERAS-2025-022, Pontotoc County
Battery storage
123 MWIn study Pontotoc, OKSPP Oct 2025target 2028
Solar project GEN-2024-123, Shelby County
Solar
120 MWIn study Shelby, TXSPP Mar 2025target 2030
Onshore wind project GEN-2025-GR2, Roosevelt County
Onshore wind
120 MWIn study Roosevelt, NMSPP Jun 2025
Solar + storage project GEN-2024-373, Choctaw County
Solar + storage
120 MWIn study Choctaw, OKSPP Mar 2025target 2029
Battery storage project GEN-2025-SR12, Noble County
Battery storage
116 MWIn study Noble, OKSPP May 2025target 2030
Battery storage project GEN-2024-295, Eddy County
Battery storage
115 MWIn study Eddy, NMSPP Mar 2025target 2030
Battery storage project GEN-2025-SR11, Noble County
Battery storage
112 MWIn study Noble, OKSPP May 2025target 2030
Solar + storage project GEN-2024-162, Dakota County
Solar + storage
110 MWIn study Dakota, NESPP Mar 2025target 2030
Gas project ERAS-2025-001, Lancaster County
Gas
104 MWIn study Lancaster, NESPP Sep 2025target 2029
Battery storage project GEN-2025-SR7, Muskogee County
Battery storage
102 MWIn study Muskogee, OKSPP May 2025target 2026
Battery storage project GEN-2024-333, Oklahoma County
Battery storage
100 MWIn study Oklahoma, OKSPP Mar 2025target 2027
Battery storage project GEN-2024-359, Stark County
Battery storage
100 MWIn study Stark, NDSPP Mar 2025target 2030
Other project GEN-2025-SR19, Chouteau County
Other
100 MWIn study Chouteau, OKSPP Jun 2025target 2029
Other project GEN-2025-SR23, Oklahoma County
Other
100 MWIn study Oklahoma, OKSPP Jun 2025target 2026
Other project GEN-2025-SR20, Douglas County
Other
100 MWIn study Douglas, NESPP Jun 2025target 2030
Battery storage project GEN-2024-375, Saline County
Battery storage
100 MWIn study Saline, MOSPP Mar 2025target 2029
Other project GEN-2025-SR21, Tulsa County
Other
100 MWIn study Tulsa, OKSPP Jun 2025target 2028
Battery storage project GEN-2024-180, Mayes County
Battery storage
100 MWIn study Mayes, OKSPP Mar 2025target 2029
Solar project GEN-2024-241, Bowie County
Solar
100 MWIn study Bowie, TXSPP Mar 2025target 2028
Other project GEN-2025-SR22, Oklahoma County
Other
100 MWIn study Oklahoma, OKSPP Jun 2025target 2028
Battery storage project GEN-2024-204, Bryan County
Battery storage
100 MWIn study Bryan, OKSPP Mar 2025target 2030
Solar project ERAS-2025-019, Edwards County
Solar
80.0 MWIn study Edwards, KSSPP Oct 2025target 2028
Solar + storage project GEN-2024-361, Lincoln County
Solar + storage
80.0 MWIn study Lincoln, OKSPP Mar 2025target 2029
Battery storage project GEN-2024-310, Chaves County
Battery storage
75.0 MWIn study Chaves, NMSPP Mar 2025target 2030
Battery storage project GEN-2025-SR29, Lea County
Battery storage
75.0 MWIn study Lea, NMSPP Aug 2025target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)