OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in SPP (Southwest Power Pool) — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown480114.8 GW
Active in queue152.4 GW692 requests
Agreement signed37.6 GW212 requests
Withdrawn1,846382.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

480 requests · page 5 of 10
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project GEN-2020-013, Harlan County
Solar + storage
215 MWIn study Harlan, NESPP Apr 2020target 2027
Battery storage project GEN-2025-SR30, Dewey County
Battery storage
209 MWIn study Dewey, OKSPP Aug 2025target 2027
Battery storage project GEN-2020-090, Bourbon County
Battery storage
204 MWIn study Bourbon, KSSPP Apr 2020target 2026
Onshore wind project GEN-2021-025, Woodward County
Onshore wind
203 MWIn study Woodward, OKSPP May 2021target 2026
Gas project GEN-2022-147, Hale County
Gas
203 MWIn study Hale, TXSPP Feb 20232025
Solar project GEN-2021-107, Pottawatomie County
Solar
202 MWIn study Pottawatomie, KSSPP May 2021target 2026
Other project GEN-2025-SR25, Tulsa County
Other
200 MWIn study Tulsa, OKSPP Jun 2025target 2028
Battery storage project GEN-2023-037, Wyandotte County
Battery storage
200 MWIn study Wyandotte, KSSPP Oct 2023target 2028
Solar project GEN-2024-228, Rice County
Solar
200 MWIn study Rice, KSSPP Mar 2025target 2030
Onshore wind project GEN-2024-058, Nowata County
Onshore wind
200 MWIn study Nowata, OKSPP Oct 2024target 2028
Battery storage project GEN-2022-155, Oklahoma County
Battery storage
200 MWIn study Oklahoma, OKSPP Feb 2023target 2027
Solar project GEN-2023-038, Coal County
Solar
200 MWIn study Coal, OKSPP Oct 2023target 2026
Other project GEN-2025-SR24, Washington County
Other
200 MWIn study Washington, NESPP Jun 2025target 2028
Other project GEN-2025-SR26, Cass County
Other
200 MWIn study Cass, NESPP Jun 2025target 2029
Solar + storage project GEN-2023-064, Le Flore County
Solar + storage
200 MWIn study Le Flore, OKSPP Oct 2023target 2029
Battery storage project GEN-2025-SR6, Grady County
Battery storage
200 MWIn study Grady, OKSPP Jun 2025target 2026
Battery storage project GEN-2022-142, Clay County
Battery storage
200 MWIn study Clay, MOSPP Feb 2023target 2030
Solar project GEN-2024-SR7, Beaver County
Solar
200 MWIn study Beaver, OKSPP Jan 2024target 2027
Solar project GEN-2024-234, Burt County
Solar
200 MWIn study Burt, NESPP Mar 2025target 2029
Solar project GEN-2024-229, Wilbarger County
Solar
200 MWIn study Wilbarger, TXSPP Mar 2025target 2030
Battery storage project GEN-2018-025, Washington County
Battery storage
200 MWPaused / redesign Washington, NESPP May 2018target 2028
Other project GEN-2023-059, Harrison County
Other
200 MWIn study Harrison, TXSPP Sep 2023target 2029
Battery storage project GEN-2022-144, Jackson County
Battery storage
200 MWIn study Jackson, MOSPP Feb 2023target 2030
Battery storage project GEN-2024-173, Lancaster County
Battery storage
200 MWIn study Lancaster, NESPP Mar 2025target 2028
Solar project GEN-2023-035, Grady County
Solar
200 MWIn study Grady, OKSPP Oct 2023target 2026
Solar project GEN-2022-055, Grady County
Solar
200 MWIn study Grady, OKSPP Jun 2022target 2029
Battery storage project GEN-2024-239, Canadian County
Battery storage
200 MWIn study Canadian, OKSPP Mar 2025target 2029
Battery storage project GEN-2022-130, Sebastian County
Battery storage
200 MWIn study Sebastian, ARSPP Feb 2023target 2030
Onshore wind project GEN-2024-365, Lea County
Onshore wind
200 MWIn study Lea, NMSPP Mar 2025target 2030
Solar project GEN-2024-154, Beckham County
Solar
200 MWIn study Beckham, OKSPP Mar 2025target 2029
Onshore wind project GEN-2024-344, Lincoln County
Onshore wind
200 MWIn study Lincoln, OKSPP Mar 2025target 2030
Battery storage project GEN-2024-061, Cowley County
Battery storage
200 MWIn study Cowley, KSSPP Oct 2024target 2028
Battery storage project GEN-2024-227, Hempstead County
Battery storage
200 MWIn study Hempstead, ARSPP Mar 2025target 2030
Battery storage project GEN-2018-033, Cass County
Battery storage
200 MWPaused / redesign Cass, NESPP May 2018target 2029
Battery storage project GEN-2022-143, Marshall County
Battery storage
200 MWIn study Marshall, OKSPP Feb 2023target 2030
Battery storage project GEN-2025-SR17, Stephens County
Battery storage
200 MWIn study Stephens, OKSPP Jun 2025target 2026
Battery storage project GEN-2024-074, Jackson County
Battery storage
200 MWIn study Jackson, MOSPP Oct 2024target 2028
Solar project GEN-2024-168, Fillmore County
Solar
200 MWIn study Fillmore, NESPP Mar 2025target 2033
Battery storage project GEN-2020-060, Lubbock County
Battery storage
200 MWIn study Lubbock, TXSPP Apr 2020target 2027
Battery storage project GEN-2022-024, Bourbon County
Battery storage
200 MWIn study Bourbon, KSSPP Jun 2022target 2028
Battery storage project GEN-2024-SR6, Johnston County
Battery storage
200 MWIn study Johnston, OKSPP Feb 2024
Onshore wind project GEN-2024-366, Lea County
Onshore wind
200 MWIn study Lea, NMSPP Mar 2025target 2030
Battery storage project GEN-2023-033, Clay County
Battery storage
200 MWIn study Clay, MOSPP Oct 2023target 2028
Solar project GEN-2022-006, Labette County
Solar
200 MWIn study Labette, KSSPP May 2022target 2028
Solar project GEN-2022-098, Johnston County
Solar
200 MWIn study Johnston, OKSPP Dec 2022target 2027
Battery storage project GEN-2024-329, Williams County
Battery storage
200 MWIn study Williams, NDSPP Mar 2025target 2028
Battery storage project GEN-2024-327, Ward County
Battery storage
200 MWIn study Ward, NDSPP Mar 2025target 2028
Battery storage project GEN-2024-175, Greene County
Battery storage
200 MWIn study Greene, MOSPP Mar 2025target 2028
Solar project GEN-2023-177, Garvin County
Solar
200 MWIn study Garvin, OKSPP Oct 2023target 2028
Battery storage project GEN-2021-040, Cass County
Battery storage
200 MWIn study Cass, NESPP Apr 2021target 2029
Page 5 of 10

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)