Interconnection queue in Michigan, MISO — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown28756.6 GW
Active in queue56.6 GW287 requests
Agreement signed4,539 MW32 requests
Withdrawn37267.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

287 requests · page 5 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J4048, Oceana County
Solar
110 MWIn study Oceana, MIMISO Aug 2025target 2028
Solar project J3858, Livingston County
Solar
110 MWIn study Livingston, MIMISO Dec 2024target 2029
Solar project J1929, Cheboygan County
Solar
110 MWIn study Cheboygan, MIMISO Aug 2021target 2025
Solar project J3857, Iosco County
Solar
105 MWIn study Iosco, MIMISO Dec 2024target 2030
Battery storage project E0004, Saginaw County
Battery storage · Hackett Energy Storage LLC
104 MWIn study Saginaw, MIMISO Aug 2025target 2027
Surplus; J199/J202
Other
100 MWIn study Tuscola, MIMISO Jul 2024target 2013
Battery storage project J3973, Branch County
Battery storage
100 MWIn study Branch, MIMISO Mar 2025target 2030
Solar project J1248, Calhoun County
Solar
100 MWAgreement signed Calhoun, MIMISO Apr 2019target 2025
Battery storage project J4128, Eaton County
Battery storage
100 MWIn study Eaton, MIMISO Sep 2025target 2030
Solar project J1430, Calhoun County
Solar
100 MWAgreement signed Calhoun, MIMISO Apr 20192023
Battery storage project J3735, Genesee County
Battery storage
100 MWIn study Genesee, MIMISO Apr 2024target 2028
Solar project J2484, Monroe County
Solar
100 MWIn study Monroe, MIMISO Sep 2022target 2025
Solar project J1071, Oceana County
Solar
100 MWUnder construction Oceana, MIMISO Mar 2018target 2021
Battery storage project J3007, Mason County
Battery storage
100 MWIn study Mason, MIMISO Aug 2022target 2025
Solar project J1375, Muskegon County
Solar
100 MWUnder construction Muskegon, MIMISO Apr 2019target 2025
Battery storage project J2064, Jackson County
Battery storage
100 MWIn study Jackson, MIMISO Nov 2021target 2024
Solar project J1331, St. Clair County
Solar
100 MWAgreement signed St. Clair, MIMISO Apr 2019target 2025
Surplus; Polaris Solar
Other
100 MWAgreement signed Gratiot, MIMISO Apr 2022target 2023
Battery storage project J1845, Calhoun County
Battery storage
100 MWIn study Calhoun, MIMISO Dec 2020target 2025
Battery storage project J1659, Washtenaw County
Battery storage
100 MWUnder construction Washtenaw, MIMISO Jun 2020target 2025
Battery storage project J2026, Gratiot County
Battery storage
100 MWIn study Gratiot, MIMISO Nov 2021target 2022
Surplus; J1375
Battery storage
100 MWIn study Muskegon, MIMISO Jan 2025target 2028
Solar project J1916, Branch County
Solar
100 MWIn study Branch, MIMISO Oct 2023target 2026
Solar + storage project J2057, Montcalm County
Solar + storage
100 MWIn study Montcalm, MIMISO Aug 2021target 2024
Battery storage project J2618, Macomb County
Battery storage
100 MWIn study Macomb, MIMISO Sep 2022target 2026
Solar project J1587, Muskegon County
Solar
100 MWAgreement signed Muskegon, MIMISO Jun 2020target 2025
Solar project J1472, Jackson County
Solar
100 MWAgreement signed Jackson, MIMISO Apr 2019target 2024
Solar project J3828, Lapeer County
Solar
100 MWIn study Lapeer, MIMISO Apr 2024target 2028
Solar project J1932, Gladwin County
Solar
100 MWIn study Gladwin, MIMISO Aug 2021target 2024
Battery storage project J3485, Huron County
Battery storage
100 MWIn study Huron, MIMISO Apr 2024target 2028
Battery storage project J2392, Mason County
Battery storage
100 MWIn study Mason, MIMISO Sep 2022target 2026
Battery storage project J3421, Huron County
Battery storage
100 MWIn study Huron, MIMISO Apr 2024target 2028
Battery storage project J3861, Branch County
Battery storage
100 MWIn study Branch, MIMISO Dec 2024target 2028
Battery storage project J3268, Gratiot County
Battery storage
100 MWIn study Gratiot, MIMISO Apr 2024target 2027
Solar project J3470, Tuscola County
Solar
100 MWIn study Tuscola, MIMISO Apr 2024target 2027
Solar + storage project J2069, Montcalm County
Solar + storage
100 MWIn study Montcalm, MIMISO Nov 2021target 2027
Battery storage project J2499, Ottawa County
Battery storage
100 MWIn study Ottawa, MIMISO Sep 2022target 2026
Solar project J1251, Marquette County
Solar
100 MWUnder construction Marquette, MIMISO Apr 2019target 2025
Battery storage project J2555, Ingham County
Battery storage
100 MWIn study Ingham, MIMISO Aug 2023target 2026
Battery storage project J1844, Washtenaw County
Battery storage
100 MWIn study Washtenaw, MIMISO Dec 2020target 2024
Solar project J2679, Livingston County
Solar
100 MWIn study Livingston, MIMISO Sep 2022target 2027
Battery storage project J1635, Branch County
Battery storage
100 MWAgreement signed Branch, MIMISO Jun 2020target 2025
Surplus; J758
Other
100 MWIn study Calhoun, MIMISO Aug 2024target 2027
Solar project J3777, Cheboygan County
Solar
91.8 MWIn study Cheboygan, MIMISO Apr 2024target 2028
Surplus; J728
Other
90.0 MWIn study Isabella, MIMISO Aug 2022target 2025
Surplus; J717
Other
90.0 MWIn study Isabella, MIMISO Aug 2022target 2025
Solar project J1399, Ingham County
Solar
90.0 MWAgreement signed Ingham, MIMISO Apr 2019target 2025
Surplus; J1224/J1329
Other
85.1 MWIn study Washtenaw, MIMISO Oct 2024target 2028
Solar project J2874, Bay County
Solar
85.0 MWIn study Bay, MIMISO Aug 2022target 2025
Solar project J3653, Washtenaw County
Solar
80.0 MWIn study Washtenaw, MIMISO Apr 2024target 2028

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20112025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)