United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESQueue requests in study in the USA — page 44
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project ERAS-2025-002, Hale County Gas |
217 MW | In study |
| Marcos Solar SLF Solar + storage · GRS BESS Texas Eight |
216 MW | In study |
| Solar project J2599, Redwood County Solar |
216 MW | In study |
| Walleye Solar Solar · Sandow Lakes Ranch Solar II, LLC |
215 MW | In study |
| Solar project J3457, Arkansas County Solar |
215 MW | In study |
| Gas project 114, Kitsap County Gas |
215 MW | Paused / redesign |
| Onshore wind project GEN-2022-176, Nowata County Onshore wind |
215 MW | In study |
| Solar project J2611, Alcona County Solar |
215 MW | In study |
| Solar + storage project GEN-2020-013, Harlan County Solar + storage |
215 MW | In study |
| Diamond Sage Solar 1 Solar + storage · DGC Renewables, LLC |
214 MW | In study |
| Diamond Sage Solar 2 Solar + storage · DGC Renewables, LLC |
214 MW | In study |
| Solar project J3940, Isabella County Solar |
214 MW | In study |
| Puerto Del Sol 2 Solar · PUERTO DEL SOL, LLC |
214 MW | In study |
| Solar + storage project Q239, Pinal County Solar + storage |
214 MW | In study |
| Solar + storage project SP106, Pinal County Solar + storage |
214 MW | In study |
| Puerto Del Sol 1 Solar · PUERTO DEL SOL, LLC |
214 MW | In study |
| Weston Storage Battery storage |
214 MW | In study |
| Sandhill Energy Storage Battery storage · Xcel Energy |
214 MW | In study |
| Frigatebird Storage Battery storage |
214 MW | In study |
| Deckerville Solar Park Project Solar · DTE Electric |
213 MW | In study |
| Gas project 11-045, Multnomah County Gas |
213 MW | Paused / redesign |
| Mesquite Creek Windpower Repower Onshore wind · Mesquite Creek Wind LLC |
213 MW | In study |
| Replacing 30 MW of existing coal generation with BESS at Burlington Generation Station; Burlington 5 Other |
212 MW | In study |
| BumbleBee Solar Solar · BumbleBee Solar Farm LLC |
212 MW | In study |
| Vazlon Solar SLF Solar + storage · Vazlon Energy LLC |
211 MW | In study |
| Gypsum Plains Storage Solar + storage · Gypsum Plains Solar, LLC |
211 MW | In study |
| Gas project J3465, Isanti County Gas |
211 MW | In study |
| Bessie Storage Battery storage · Bessie Energy Storage, LLC |
211 MW | In study |
| Val Vista Grid BESS 2 Battery storage · Val Vista Grid, LLC |
211 MW | In study |
| Guadalupe Battery Storage Project Battery storage · Guadalupe Power Partners, LP |
211 MW | In study |
| Freestone Battery Storage Project Battery storage · Freestone Power Generation, LLC |
211 MW | In study |
| Solar project J2811, Cerro Gordo County Solar |
210 MW | In study |
| Hydro project G0535, Walla Walla County Hydro |
210 MW | In study |
| Battery storage project S0027, Walla Walla County Battery storage |
210 MW | In study |
| Solar project AG2-245, Starke County Solar · STARKE CENTRAL PROJECT, LLC |
210 MW | In study |
| Battery storage project AI1-185, Augusta County Battery storage |
210 MW | In study |
| Solar project AG2-184, Knott County Solar · STMO bn, LLC |
210 MW | In study |
| Elk Unit 4 Gas · Golden Spread Electric Cooperative, Inc. |
210 MW | In study |
| Solar project J2553, Cerro Gordo County Solar |
210 MW | In study |
| Solar + storage project AH2-419, Laporte County Solar + storage |
210 MW | In study |
| Broomstick Solar Energy Centergy Center Solar |
210 MW | Paused / redesign |
| Other project IA-PNM-2023-10, Mckinley County Other |
210 MW | In study |
| Alamosa Solar Solar |
210 MW | Paused / redesign |
| Val Vista Grid BESS 1 Battery storage · Val Vista Grid, LLC |
209 MW | In study |
| Moonlit Bayou Storage Battery storage · Moonlit Bayou Energy Center, LLC |
209 MW | In study |
| Treehouse Storage Solar + storage · Treehouse Solar, LLC |
209 MW | In study |
| Battery storage project GEN-2025-SR30, Dewey County Battery storage |
209 MW | In study |
| Gas project 200, Anderson County Gas |
209 MW | In study |
| Clapton Storage Solar + storage · Clapton BESS |
209 MW | In study |
| Sisters Storage Solar + storage · 174 Power Global Properties |
209 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)1,496 · 455.6 GW
- ERCOT (Texas)1,408 · 328.0 GW
- MISO (Midcontinent)1,337 · 302.2 GW
- Southeast (non-ISO utilities)815 · 118.5 GW
- SPP (Southwest Power Pool)480 · 114.8 GW
- PJM (Mid-Atlantic, Midwest)905 · 105.4 GW
- CAISO (California)194 · 92.4 GW
- NYISO (New York)190 · 27.1 GW
- ISO-NE (New England)27 · 6,015 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)