Solar + storage project Q239, Pinal County

Solar + storage project Q239, Pinal County is a 214 MW solar + storage request in interconnection study in the West interconnection queue, in Pinal County, Arizona, connecting to Arizona Public Service.

Queue statusIn planning
  1. PlanningQueued Mar 2016 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2021 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q239
Grid region
West (non-ISO utilities)
Utility / transmission owner
Arizona Public Service
Connection point (POI)
Saguaro Substation 230kV
Location
Pinal County, Arizona
Technology
Solar: 214 MW · Battery
Total requested
214 MW
Service type
Network resource (NRIS)
Study phase
Project with APS Project Manager (Legacy)
Queue status
Active
Entered queue
30 March 2016
Proposed online date
March 2021

Location

Marker shows the centre of Pinal County; the queue data does not give exact sites.

Power plants in Arizona · Transmission lines in Arizona

Other requests in Pinal County