Withdrawn queue requests in the USA — page 43

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 43 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-2016-25, Kit Carson County
Onshore wind
500 MWWithdrawn / abandoned Kit Carson, COWest Oct 2016target 2020
Onshore wind project C2-108, Sweetwater County
Onshore wind
500 MWWithdrawn / abandoned Sweetwater, WYWest May 2022target 2025
Greasewood Energy Storage II
Battery storage
500 MWWithdrawn / abandoned CACAISO Apr 2023target 2033
Onshore wind project AD2-015, Benton County
Onshore wind
500 MWWithdrawn / abandoned Benton, INPJM Nov 2017target 2020
Solar project 597, Mississippi County
Solar
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023
Solar project 383, Lawrence County
Solar
500 MWWithdrawn / abandoned Lawrence, ALSoutheast Jul 2019
Avalon II
Onshore wind
500 MWWithdrawn / abandoned Kern, CACAISO May 2008target 2011
Blooming Grove Power
Other · Titan Development, LLC
500 MWWithdrawn / abandoned NYNYISO Jul 2001
Gas project B49, Warren County
Gas
500 MWWithdrawn / abandoned Warren, PAPJM Nov 1999
Grange Solar
Solar
500 MWWithdrawn / abandoned Logan, OHPJM Mar 2020target 2029
500MW Taft-Bell
Gas · Cogentrix Energy, Inc.
500 MWWithdrawn / abandoned Kootenai, IDWest Dec 2000target 2004
Gas project B33, Dauphin County
Gas
500 MWWithdrawn / abandoned Dauphin, PAPJM Nov 1999target 2005
Solar project C3-114, Iron County
Solar
500 MWWithdrawn / abandoned Iron, UTWest May 2023target 2026
Other project G029, Lawrence County
Other
500 MWWithdrawn / abandoned Lawrence, INMISO Jan 2000target 2002
Solar + storage project Q491, Yuma County
Solar + storage
500 MWWithdrawn / abandoned Yuma, AZWest Sep 2022target 2026
Solar project J3530, Saline County
Solar
500 MWWithdrawn / abandoned Saline, ARMISO Apr 2024target 2028
Solar project GEN-2018-044, Antelope County
Solar
500 MWWithdrawn / abandoned Antelope, NESPP May 20182025
Battery storage project G0560, Grant County
Battery storage
500 MWWithdrawn / abandoned Grant, WAWest Mar 2017target 2025
Solar + storage project IA-PNM-2022-08, Curry County
Solar + storage
500 MWWithdrawn / abandoned Curry, NMWest Apr 2022target 2025
Solar + storage project Company PI, Humboldt County
Solar + storage
500 MWWithdrawn / abandoned Humboldt, NVWest Mar 2022target 2029
Solar + storage project Company PA, Esmeralda County
Solar + storage
500 MWWithdrawn / abandoned Esmeralda, NVWest Jan 2023target 2026
Solar project AG1-178, Sussex County
Solar · Cabin Point Solar, LLC
500 MWWithdrawn / abandoned Sussex, VAPJM Sep 2020target 2023
Onshore wind project Q40, Coconino County
Onshore wind
500 MWWithdrawn / abandoned Coconino, AZWest Dec 2007target 2015
Onshore wind project Q73, Apache County
Onshore wind
500 MWWithdrawn / abandoned Apache, AZWest Apr 2021target 2028
Battery storage project Q511, Coconino County
Battery storage
500 MWWithdrawn / abandoned Coconino, AZWest Mar 2023target 2028
Solar + storage project Q70, Kern County
Solar + storage
500 MWWithdrawn / abandoned Kern, CAWest May 2019target 2022
Gas project G06_W44, Monongalia County
Gas
500 MWWithdrawn / abandoned Monongalia, WVPJM Feb 2001target 2005
Solar project Q55, Kern County
Solar
500 MWWithdrawn / abandoned Kern, CAWest Aug 2016target 2021
Solar + storage project AE1-216, White County
Solar + storage
500 MWWithdrawn / abandoned White, INPJM Sep 2018target 2023
Other project J2697, St. Clair County
Other
500 MWWithdrawn / abandoned St. Clair, ILMISO Sep 2022target 2027
Solar project GEN-2020-085, Carter County
Solar
500 MWWithdrawn / abandoned Carter, OKSPP Apr 2020target 2026
Gas project H14_W67
Gas
500 MWWithdrawn / abandoned PAPJM Dec 2001target 2007
500MW Custer-[Intalco,Portal Way] 1
Gas · Calpine Energy Services, L.P.
500 MWWithdrawn / abandoned Whatcom, WAWest Feb 2001target 2005
Onshore wind project 135, Converse County
Onshore wind · Clipper Windpower Development Company, Inc
500 MWWithdrawn / abandoned Converse, WYWest May 2007target 2011
Onshore wind project 2017-G6
Onshore wind
500 MWWithdrawn / abandoned West Aug 2017target 2020
Solar + storage project Company NN, Storey County
Solar + storage
500 MWWithdrawn / abandoned Storey, NVWest Mar 2022target 2025
Oyster Shore BESS
Battery storage · Juno Power Management LLC
500 MWWithdrawn / abandoned Nassau, NYNYISO Aug 2020
Gas project H25, Somerset County
Gas
500 MWWithdrawn / abandoned Somerset, PAPJM Jan 2002target 2007
Solar project Q07, Maricopa County
Solar
500 MWWithdrawn / abandoned Maricopa, AZWest Dec 2008target 2013
Battery storage project IC-1117, Fulton County
Battery storage
500 MWWithdrawn / abandoned Fulton, GASoutheast Feb 2023
Fresh Kills Energy Storage
Battery storage · Fresh Kills Battery Storage LLC
500 MWWithdrawn / abandoned Richmond, NYNYISO Mar 2022
Gas project J167, Dakota County
Gas
500 MWWithdrawn / abandoned Dakota, MNMISO Sep 2010target 2010
Desert Sapphire PV
Solar
500 MWWithdrawn / abandoned Kern, CACAISO Mar 2007target 2015
Geothermal project Q103, Inyo County
Geothermal
500 MWWithdrawn / abandoned Inyo, CAWest Jun 2023target 2027
Solar project AD2-197, Greensville County
Solar
500 MWWithdrawn / abandoned Greensville, VAPJM Mar 2018target 2021
Blythe Mesa Solar II
Solar
500 MWWithdrawn / abandoned Riverside, CACAISO Nov 2011target 2015
Buchanan Energy
Other · Titan Development, LLC
500 MWWithdrawn / abandoned NYNYISO Feb 2001
Solar + storage project Company 247, Nye County
Solar + storage
500 MWWithdrawn / abandoned Nye, NVWest Mar 2023target 2027
Solar + storage project Q428, Navajo County
Solar + storage
500 MWWithdrawn / abandoned Navajo, AZWest Sep 2021target 2024
Solar + storage project GEN-2024-302, Roosevelt County
Solar + storage
500 MWWithdrawn / abandoned Roosevelt, NMSPP Mar 2025target 2029
Page 43 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)