United States βΊ Grid βΊ Interconnection queues βΊ Nevada
SOLAR + STORAGE Β· WESTSolar + storage project Company PI, Humboldt County
Solar + storage project Company PI, Humboldt County is a 500 MW solar + storage request withdrawn in the West interconnection queue, in Humboldt County, Nevada, connecting to NV Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2022 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- Company PI
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NV Energy
- Location
- Humboldt County, Nevada
- Technology
- Solar: 500 MW Β· Battery
- Total requested
- 500 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 16 March 2022
- Proposed online date
- January 2029
Location
Marker shows the centre of Humboldt County; the queue data does not give exact sites.
Other requests in Humboldt County
- Solar project Company IF, Humboldt CountySolar Β· 350 MW Β· agreement signed
- Solar + storage project Company KN, Humboldt CountySolar + storage Β· 250 MW Β· agreement signed
- Solar + storage project Company MG, Humboldt CountySolar + storage Β· 170 MW Β· agreement signed
- Solar project Company IG, Humboldt CountySolar Β· 150 MW Β· agreement signed
- Geothermal project 25-00412, Humboldt CountyGeothermal Β· 600 MW Β· in study
- Solar + storage project 25-00416, Humboldt CountySolar + storage Β· 600 MW Β· in study
- Gas project Company QF, Humboldt CountyGas Β· 218 MW Β· in study
- Gas project Company QG, Humboldt CountyGas Β· 218 MW Β· in study
- Geothermal project 25-00410, Humboldt CountyGeothermal Β· 200 MW Β· in study
- Geothermal project 25-00411, Humboldt CountyGeothermal Β· 200 MW Β· in study
- Geothermal project 25N-SG3, Humboldt CountyGeothermal Β· 20.0 MW Β· in study
- Geothermal project 25N-SG4, Humboldt CountyGeothermal Β· 20.0 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem