πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

ONSHORE WIND Β· WEST

Onshore wind project GI-2016-25, Kit Carson County

Onshore wind project GI-2016-25, Kit Carson County is a 500 MW onshore wind request withdrawn in the West interconnection queue, in Kit Carson County, Colorado, connecting to Public Service Company Of Colorado.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2016 (completed)
  2. Withdrawn / abandonedJan 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-2016-25
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company Of Colorado
Connection point (POI)
Missile Site Substation 345kV
Location
Kit Carson County, Colorado
Technology
Wind: 500 MW
Total requested
500 MW
Service type
NRIS and ERIS
Study phase
Feasibility Study Complete System Impact Study Complete Facility Study Underway Request Withdrawn 01/06/2020
Queue status
Withdrawn
Entered queue
6 October 2016
Proposed online date
October 2020
Withdrawn
January 2020

Location

Marker shows the centre of Kit Carson County; the queue data does not give exact sites.

Power plants in Colorado Β· Transmission lines in Colorado

Other requests in Kit Carson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem