Queue requests in study in the USA (2023 requests) โ€” page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,065262.8 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,065 requests ยท page 4 of 22
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project Q538, Coconino County
Onshore wind
500 MWIn study Coconino, AZWest Sep 2023target 2027
Cantus
Solar + storage
499 MWIn study Merced, CACAISO Apr 2023target 2031
Battery storage project G0941, Gilliam County
Battery storage
488 MWIn study Gilliam, ORWest Sep 2023target 2028
Gas project GEN-2023-222, Gage County
Gas
478 MWIn study Gage, NESPP Oct 2023target 2030
Gas project GEN-2023-224, Lancaster County
Gas
478 MWIn study Lancaster, NESPP Oct 2023target 2029
Solar + storage project GEN-2023-102, Woods County
Solar + storage
475 MWIn study Woods, OKSPP Oct 2023target 2029
Shoals Energy Storage 2
Battery storage
461 MWIn study Los Angeles, CACAISO Apr 2023target 2029
Solar + storage project Company 218, Clark County
Solar + storage
460 MWPaused / redesign Clark, NVWest Mar 2023target 2029
Salt-Lick Solar
Solar + storage ยท Salt-Lick Solar, LLC
453 MWIn study Culberson, TXERCOT Oct 2023target 2028
TRIFECTA Gas
Gas ยท NET Power
453 MWIn study Midland, TXERCOT Jun 2023target 2030
Gas project 2023-G13, La Paz County
Gas
453 MWIn study La Paz, AZWest Oct 2023target 2027
Solar + storage project Company OF, Lander County
Solar + storage
450 MWPaused / redesign Lander, NVWest Jan 2023target 2028
Aurelius 2 Solar
Solar ยท IP Roman, LLC
445 MWIn study Deaf Smith, TXERCOT Dec 2023target 2028
Aurelius 3 Solar
Solar ยท IP Roman III, LLC
445 MWIn study Deaf Smith, TXERCOT Dec 2023target 2029
Gas project Q40, Maricopa County
Gas
425 MWIn study Maricopa, AZWest Aug 2023target 2028
Solar + storage project G0844, Klickitat County
Solar + storage
420 MWIn study Klickitat, WAWest Feb 2023target 2026
Whiskey Diggings
Solar
414 MWIn study Sutter, CACAISO Apr 2023target 2030
Western Flats Solar
Solar + storage ยท Hecate Energy Point Mountain Solar Facility 1 LLC
410 MWIn study Crane, TXERCOT Apr 2023target 2028
Silverton Solar
Solar ยท NextEra Energy Interconnection Holdings, LLC
410 MWIn study Briscoe, TXERCOT Dec 2023target 2029
Solstice C
Solar + storage
408 MWIn study Fresno, CACAISO Apr 2023target 2031
Solstice D
Solar + storage
408 MWIn study Fresno, CACAISO Apr 2023target 2031
Lund Storage Center 1
Battery storage ยท Lund Storage Center 1, LLC
408 MWIn study Bastrop, TXERCOT Jan 2023target 2026
Maravillosa 1
Solar + storage
407 MWIn study Kings, CACAISO Apr 2023target 2029
Claire BESS
Battery storage ยท BRP Blue Topaz 3, LLC
406 MWIn study Harris, TXERCOT Feb 2023target 2027
Tea Leaf Energy Storage
Battery storage
404 MWIn study Alameda, CACAISO Apr 2023target 2030
Gas project IC-1160, Shelby County
Gas
403 MWPaused / redesign Shelby, ALSoutheast Aug 2023target 2030
Gas project IC-1159, Shelby County
Gas
403 MWPaused / redesign Shelby, ALSoutheast Aug 2023target 2030
Solar project G1035, Douglas County
Solar
400 MWIn study Douglas, WAWest Nov 2023target 2028
Solar + storage project Q537, Pinal County
Solar + storage
400 MWIn study Pinal, AZWest Sep 2023target 2027
Onshore wind project GI-2023-14, Morgan County
Onshore wind
400 MWPaused / redesign Morgan, COWest May 2023target 2026
Gamay
Solar + storage
400 MWIn study Kern, CACAISO Apr 2023target 2031
Battery storage project 23-221, Washington County
Battery storage
400 MWIn study Washington, ORWest Mar 2023target 2027
Other project G0895, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Other project G0893, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Solar + storage project G0887, Douglas County
Solar + storage
400 MWIn study Douglas, ORWest Jun 2023target 2030
Solar + storage project G0979, Klickitat County
Solar + storage
400 MWIn study Klickitat, WAWest Nov 2023target 2029
Solar + storage project G0901, Linn County
Solar + storage
400 MWIn study Linn, ORWest Jun 2023target 2030
Solar project G1016, Klickitat County
Solar
400 MWIn study Klickitat, WAWest Nov 2023target 2029
Solar + storage project Q507, Maricopa County
Solar + storage
400 MWIn study Maricopa, AZWest Mar 2023target 2028
Solar + storage project G0888, Lane County
Solar + storage
400 MWIn study Lane, ORWest Jun 2023target 2030
Solar + storage project G0900, Linn County
Solar + storage
400 MWIn study Linn, ORWest Jun 2023target 2030
Solar + storage project G0910, Deschutes County
Solar + storage
400 MWIn study Deschutes, ORWest Jul 2023target 2030
Other project G0904, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Solar + storage project C3-041, Harney County
Solar + storage ยท Lone Pine Energy, LLC
400 MWPaused / redesign Harney, ORWest May 2023target 2026
Other project G0899, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Other project G0902, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Boling Generation (TEF-Due Diligience)
Gas ยท Boling Generation
400 MWIn study Wharton, TXERCOT Dec 2023target 2027
Solar + storage project G0912, Deschutes County
Solar + storage
400 MWIn study Deschutes, ORWest Jul 2023target 2033
Other project G0905, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030
Other project G0894, Linn County
Other
400 MWIn study Linn, ORWest Jun 2023target 2030

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)