United States › Grid › Interconnection queues › Massachusetts
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Massachusetts — page 4
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Biomass Project ( Also see queue position #223) Other |
62.0 MW | Withdrawn / abandoned |
| Eversource Group Study @ Wareham Solar + storage |
55.1 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
55.0 MW | Withdrawn / abandoned |
| Gas Turbine Capacity Increase (see #155) Gas |
55.0 MW | Withdrawn / abandoned |
| Russell Biomass Other |
55.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
50.0 MW | Withdrawn / abandoned |
| Energy Storage Battery storage |
50.0 MW | Withdrawn / abandoned |
| Biomass Project Other |
49.7 MW | Withdrawn / abandoned |
| Biomass Project Other |
49.7 MW | Withdrawn / abandoned |
| Eversource Group @ Wareham 714 Solar + storage |
48.0 MW | Withdrawn / abandoned |
| Eversource Group @ West Pond 737 Solar + storage |
44.1 MW | Withdrawn / abandoned |
| Bear Swamp Uprate - First Unit Battery storage |
43.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
41.2 MW | Withdrawn / abandoned |
| Combined Cycle Upgrade #1 Gas |
40.6 MW | Withdrawn / abandoned |
| Offshore Wind Increase Offshore wind |
40.0 MW | Withdrawn / abandoned |
| Solar Solar |
40.0 MW | Withdrawn / abandoned |
| (Offshore wind Increase (Q700 +Q1154) Offshore wind |
38.8 MW | Withdrawn / abandoned |
| Palmer Renewable Energy Other |
36.7 MW | Withdrawn / abandoned |
| E. Winchendon Substation - NG WMA Group 3 Solar + storage |
35.0 MW | Withdrawn / abandoned |
| Repowering Increase Gas |
34.8 MW | Withdrawn / abandoned |
| Eversource Group @ Tremont Substation 713 Solar + storage |
33.7 MW | Withdrawn / abandoned |
| Combined Cycle Upgrate #3 Gas |
30.0 MW | Withdrawn / abandoned |
| Wind Onshore wind |
30.0 MW | Withdrawn / abandoned |
| Eversource Group @ Industrial Park 636 Solar + storage |
29.1 MW | Withdrawn / abandoned |
| Gas Turbine (Additional Capacity) Other |
29.0 MW | Withdrawn / abandoned |
| EE Group @ Blandford Solar + storage |
28.9 MW | Withdrawn / abandoned |
| Wendall Depot Substation - NG WMA Group 3 Solar + storage |
28.0 MW | Withdrawn / abandoned |
| Eversource Group @ Fisher Rd Substation 657 Solar + storage |
27.9 MW | Withdrawn / abandoned |
| Snow St. Substation - NG WMA Group 3 Solar + storage |
27.8 MW | Withdrawn / abandoned |
| Whitmanville substation - NG Western MA Area Cluster Study Solar |
26.6 MW | Withdrawn / abandoned |
| Snow Street substation - NG Western MA Area Cluster Study Solar |
24.7 MW | Withdrawn / abandoned |
| Eversource Group @ Rochester #745 Solar + storage |
24.6 MW | Withdrawn / abandoned |
| Brookfield substation - NG Western MA Area Cluster Study Solar |
24.0 MW | Withdrawn / abandoned |
| Stafford St. Substation - NG WMA Group 3 Solar + storage |
22.4 MW | Withdrawn / abandoned |
| Combined Cycle Increase Gas |
22.0 MW | Withdrawn / abandoned |
| New Salem substation - NG Western MA Area Cluster Study Solar |
21.3 MW | Withdrawn / abandoned |
| Eversource Group Study @ Crystal Spring Solar + storage |
20.5 MW | Withdrawn / abandoned |
| N. Oxford Substation - NG WMA Group 3 Solar + storage |
20.4 MW | Withdrawn / abandoned |
| Stafford Street substation - NG Western MA Area Cluster Study Solar |
20.4 MW | Withdrawn / abandoned |
| Combined Cycle Increase Gas |
20.2 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
20.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
20.0 MW | Withdrawn / abandoned |
| solar with battery Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
20.0 MW | Withdrawn / abandoned |
| Shutesbury substation - NG Western MA Area Cluster Study Solar |
20.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
20.0 MW | Withdrawn / abandoned |
| W. Charlton Substation - NG WMA Group 3 Battery storage |
20.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
20.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)