SOLAR + STORAGE · ISO-NE

solar with battery

solar with battery is a 20.0 MW solar + storage request withdrawn in the ISO-NE interconnection queue, in Worcester County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2017 (completed)
  2. Withdrawn / abandonedJul 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
682
Grid region
ISO-NE (New England)
Connection point (POI)
National Grid 13.8kV circuit (E.-Winchendon Substation) on Winchendon Road (near Depot Road), Winchendon, MA
Location
Worcester County, Massachusetts
Technology
Solar: 20.0 MW · Battery
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
18 September 2017
Proposed online date
December 2020
Withdrawn
July 2018

Location

Marker shows the centre of Worcester County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Worcester County