United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Completed queue projects in PJM (Mid-Atlantic, Midwest) — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,19297.6 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,192 requests · page 4 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Honeysuckle Solar Project
Solar
150 MWOperating St. Joseph, INPJM Sep 20192025
Other project V4-007
Other
150 MWOperating PJM Nov 2009target 2012
Colonial Trail West Solar
Solar
142 MWOperating Surry, VAPJM Apr 20162019
Lordstown Energy Center
Gas
140 MWOperating Trumbull, OHPJM Jun 20152018
Quad Cities - Units 1 & 2
Nuclear
140 MWOperating Rock Island, ILPJM Jun 20062011
Holtwood
Hydro
140 MWOperating Lancaster, PAPJM Mar 20062010
Peach Bottom - Units 2 & 3
Nuclear
140 MWOperating York, PAPJM Jun 20062012
Twin Ridges Wind Farm
Onshore wind
139 MWOperating Somerset, PAPJM Jul 20082012
Bitter Ridge Wind Farm
Onshore wind
130 MWOperating Jay, INPJM Mar 20172020
Perryman 6 Units 1-4
Gas
130 MWOperating Harford, MDPJM May 20072015
Hardin Energy Center
Solar
130 MWOperating Hardin, OHPJM Apr 20162020
Hilltop Energy Center Facility
Gas
130 MWOperating Greene, PAPJM Mar 20172021
Yellowbud Solar
Solar
127 MWOperating Ross, OHPJM Feb 20172022
Yellowbud Solar
Solar
127 MWOperating Ross, OHPJM Nov 20172022
Bookers Mill Solar
Solar
127 MWOperating City Of Richmond, VAPJM Sep 20182024
Hunlock Creek
Gas
126 MWOperating Luzerne, PAPJM Dec 20072011
Hillcrest Solar Facility
Solar
125 MWOperating Brown, OHPJM Jun 20152020
Wheatsborough Solar
Solar
125 MWOperating Erie, OHPJM Mar 20192025
Bluff Point
Onshore wind
120 MWOperating Jay, INPJM Jul 20072017
Delta York
Gas
120 MWOperating York, PAPJM Jul 20142018
Linden 5 & 6
Gas
120 MWOperating Union, NJPJM Apr 19972000
Summit Farms Solar and Ranchland Solar
Solar
120 MWOperating Currituck, NCPJM Oct 20142018
Oak Solar
Solar
120 MWOperating Northampton, NCPJM Nov 20152024
Shillelagh Solar
Solar
118 MWOperating City Of Chesapeake, VAPJM Dec 20162023
Perry Road Solar
Solar
118 MWOperating Somerset, MDPJM Oct 20142017
Dodson Creek Solar
Solar
117 MWOperating Ross, OHPJM Feb 20172025
Salem 1 & 2
Nuclear
115 MWOperating Salem, NJPJM Jan 20022008
Calpine Parlin Energy Center
Gas
114 MWOperating Middlesex, NJPJM Apr 20072008
Lackawanna Thermal Generating Station
Gas
113 MWOperating Lackawanna, PAPJM Oct 20142019
Meldahl Hydroelectric Plant
Hydro
112 MWOperating Butler, OHPJM Sep 20092015
Susquehanna #1
Nuclear
111 MWOperating Luzerne, PAPJM May 20042010
Smithton Generation Station
Gas
110 MWOperating Westmoreland, PAPJM Jul 20162018
Black Rock Wind
Onshore wind
110 MWOperating Mineral, WVPJM Mar 20182021
Holtwood
Hydro
107 MWOperating Lancaster, PAPJM Jul 20012002
Susquehanna #2
Nuclear
107 MWOperating Luzerne, PAPJM May 20042011
South Bend CT1 - CT4
Gas
104 MWOperating Armstrong, PAPJM May 20012003
New Creek Mountain Wind Farm
Onshore wind
103 MWOperating Mineral, WVPJM Jan 20082016
D.C. Cook Generating Plant Unit No. 2
Nuclear
102 MWOperating Berrien, MIPJM Aug 20132017
Ford Mill
Gas
101 MWOperating Bucks, PAPJM Jan 20072010
Gould Street
Gas
101 MWOperating Baltimore City, MDPJM Jul 20072008
Midland Wind Farm
Onshore wind
101 MWOperating Henry, ILPJM Aug 20162024
Aspen Road Solar
Solar
100 MWOperating Franklin, PAPJM Jul 20182025
DEMEC/Smyrna 1 &2
Gas
100 MWOperating Kent, DEPJM Jul 20002002
Moccasin Creek Solar
Solar
100 MWOperating Edgecombe, NCPJM Mar 20162020
CPV Maple Hill Solar
Solar
100 MWOperating Cambria, PAPJM Mar 20192023
Armenia Mountain WF
Onshore wind
100 MWOperating Bradford, PAPJM Jan 20062009
Maplewood Solar
Solar
100 MWOperating Pittsylvania, VAPJM Sep 20162022
Riverstart Solar Park
Solar
100 MWOperating Randolph, INPJM Oct 20162021
CPV Fairview Energy Center
Gas
100 MWOperating Cambria, PAPJM Oct 20162019
Longview ST1
Coal
100 MWOperating Monongalia, WVPJM Jul 20062010
Page 4 of 24

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)