GAS · PJMPerryman 6 Units 1-4
Perryman 6 Units 1-4 is a 130 MW gas request built and operating in the PJM interconnection queue, in Harford County, Maryland, connecting to BGE.
Request details
- Queue ID
- S32
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- BGE
- Connection point (POI)
- Perryman
- Location
- Harford County, Maryland
- Technology
- Gas: 130 MW
- Total requested
- 130 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 3 May 2007
- Agreement signed
- 30 August 2012
- Proposed online date
- December 2015
- Came online
- May 2015
Location
Marker shows the centre of Harford County; the queue data does not give exact sites.
Other requests in Harford County
- Battery storage project AH1-725, Harford CountyBattery storage · 500 MW · in study
- ConowingoHydro · 36.0 MW · built
- Conowingo Hydro StationHydro · 24.0 MW · built
- Fairview Farms ISolar · 15.0 MW · built
- Fairview Farms IISolar · 15.0 MW · built
- Perryman 51Coal · 10.0 MW · built
- Perryman Generating Unit 51Gas · 10.0 MW · built
- Kingsville SolarSolar · 1.1 MW · built
- Gas project B29, Harford CountyGas · 750 MW · withdrawn
- Gas project A47, Harford CountyGas · 740 MW · withdrawn
- Gas project C12, Harford CountyGas · 550 MW · withdrawn
- Gas project C13, Harford CountyGas · 550 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem