Perryman Generating Unit 51

Perryman Generating Unit 51 is a 10.0 MW gas request built and operating in the PJM interconnection queue, in Harford County, Maryland, connecting to BGE.

Queue statusOperating
  1. PlanningQueued Jan 2008 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
T147
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
BGE
Connection point (POI)
Perryman
Location
Harford County, Maryland
Technology
Gas: 10.0 MW
Total requested
10.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
24 January 2008
Proposed online date
June 2008
Came online
June 2008

Location

Marker shows the centre of Harford County; the queue data does not give exact sites.

Power plants in Maryland · Transmission lines in Maryland

Other requests in Harford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem