United States › Grid › Interconnection queues › Ohio
HYDRO · PJMMeldahl Hydroelectric Plant
Meldahl Hydroelectric Plant is a 112 MW hydro request built and operating in the PJM interconnection queue, in Butler County, Ohio, connecting to DEOK.
Request details
- Queue ID
- V3-045
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- DEOK
- Connection point (POI)
- Zimmer-Spurlock 345kV
- Location
- Butler County, Ohio
- Technology
- Hydro: 112 MW
- Total requested
- 112 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 29 September 2009
- Agreement signed
- 20 August 2012
- Proposed online date
- December 2015
- Came online
- November 2015
Location
Marker shows the centre of Butler County; the queue data does not give exact sites.
Other requests in Butler County
- Woodsdale Renewable Energy CenterSolar · 49.0 MW · agreement signed
- Solar project AI1-092, Butler CountySolar · 49.9 MW · in study
- Solar + storage project AI1-150, Butler CountySolar + storage · 49.9 MW · in study
- Middletown Energy CenterGas · 513 MW · built
- Other project G941, Butler CountyOther · 67.0 MW · built
- Coal project G837, Butler CountyCoal · 25.0 MW · built
- Other project G098, Butler CountyOther · 165 MW · withdrawn
- Gas project W1-058A_DK1, Butler CountyGas · 135 MW · withdrawn
- Gas project J120, Butler CountyGas · 135 MW · withdrawn
- Solar project AD2-146, Butler CountySolar · 100 MW · withdrawn
- Solar project AD2-147, Butler CountySolar · 100 MW · withdrawn
- Battery storage project AG2-664, Butler CountyBattery storage · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem