United States › Grid › Interconnection queues › Ohio
COAL · MISOCoal project G837, Butler County
Coal project G837, Butler County is a 25.0 MW coal request built and operating in the MISO interconnection queue, in Butler County, Ohio.
Request details
- Queue ID
- G837
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- 601 N B Street existing co-generation systems
- Location
- Butler County, Ohio
- Technology
- Coal: 25.0 MW
- Total requested
- 25.0 MW
- Study phase
- Network Upgrade
- Queue status
- Operational
- Entered queue
- 10 August 2007
- Agreement signed
- 27 May 2008
- Proposed online date
- September 2010
- Came online
- September 2010
Location
Marker shows the centre of Butler County; the queue data does not give exact sites.
Other requests in Butler County
- Woodsdale Renewable Energy CenterSolar · 49.0 MW · agreement signed
- Solar project AI1-092, Butler CountySolar · 49.9 MW · in study
- Solar + storage project AI1-150, Butler CountySolar + storage · 49.9 MW · in study
- Middletown Energy CenterGas · 513 MW · built
- Meldahl Hydroelectric PlantHydro · 112 MW · built
- Other project G941, Butler CountyOther · 67.0 MW · built
- Other project G098, Butler CountyOther · 165 MW · withdrawn
- Gas project W1-058A_DK1, Butler CountyGas · 135 MW · withdrawn
- Gas project J120, Butler CountyGas · 135 MW · withdrawn
- Solar project AD2-146, Butler CountySolar · 100 MW · withdrawn
- Solar project AD2-147, Butler CountySolar · 100 MW · withdrawn
- Battery storage project AG2-664, Butler CountyBattery storage · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem