ONSHORE WIND Β· PJMBluff Point
Bluff Point is a 120 MW onshore wind request built and operating in the PJM interconnection queue, in Jay County, Indiana, connecting to AEP.
Request details
- Queue ID
- S71
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Bluff Point 138kV
- Location
- Jay County, Indiana
- Technology
- Wind: 120 MW
- Total requested
- 120 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 30 July 2007
- Agreement signed
- 23 April 2013
- Proposed online date
- December 2017
- Came online
- September 2017
Location
Marker shows the centre of Jay County; the queue data does not give exact sites.
Other requests in Jay County
- Skycrest Solar Energy CenterSolar Β· 155 MW Β· agreement signed
- Blackford Solar Energy ProjectSolar Β· 150 MW Β· agreement signed
- Sun Chief Solar FarmSolar Β· 100 MW Β· agreement signed
- New Jay PV & BESSSolar + storage Β· 39.0 MW Β· agreement signed
- Bitter Ridge Wind FarmOnshore wind Β· 12.6 MW Β· agreement signed
- Solar + storage project AI1-081, Jay CountySolar + storage Β· 100 MW Β· in study
- Battery storage project AH2-227, Jay CountyBattery storage Β· 75.0 MW Β· in study
- Solar project AH2-223, Jay CountySolar Β· 50.0 MW Β· in study
- Battery storage project AH2-371, Jay CountyBattery storage Β· 50.0 MW Β· in study
- Solar project AI2-422, Jay CountySolar Β· 12.0 MW Β· in study
- Solar project AI2-423, Jay CountySolar Β· 12.0 MW Β· in study
- Bitter Ridge Wind FarmOnshore wind Β· 130 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem