United States › Grid › Interconnection queues › Virginia

SOLAR · PJM

Maplewood Solar

Maplewood Solar is a 100 MW solar request built and operating in the PJM interconnection queue, in Pittsylvania County, Virginia, connecting to AEP.

Queue statusOperating
  1. PlanningQueued Sep 2016 (completed)
  2. ConsentedJan 2021 (completed)
  3. Construction (completed)
  4. OperatingSep 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AC1-083
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Smith Mountain-Bearskin 138kV
Location
Pittsylvania County, Virginia
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
30 September 2016
Agreement signed
18 January 2021
Proposed online date
May 2022
Came online
September 2022

Location

Marker shows the centre of Pittsylvania County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Pittsylvania County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem