Moccasin Creek Solar

Moccasin Creek Solar is a 100 MW solar request built and operating in the PJM interconnection queue, in Edgecombe County, North Carolina, connecting to Dominion.

Queue statusOperating
  1. PlanningQueued Mar 2016 (completed)
  2. ConsentedOct 2018 (completed)
  3. Construction (completed)
  4. OperatingOct 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AB2-059
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Benson-Dunbar 115kV
Location
Edgecombe County, North Carolina
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
25 March 2016
Agreement signed
3 October 2018
Proposed online date
June 2020
Came online
October 2020

Location

Marker shows the centre of Edgecombe County; the queue data does not give exact sites.

Power plants in North Carolina · Transmission lines in North Carolina

Other requests in Edgecombe County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem