United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 356

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 356 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 174146, Union County
Solar
31.0 MWWithdrawn / abandoned Union, NCSoutheast May 2021
Hydro project 29, Skagit County
Hydro
31.0 MWWithdrawn / abandoned Skagit, WAWest Jan 2011target 2013
Gas project AB2-101, Marshall County
Gas
31.0 MWWithdrawn / abandoned Marshall, WVPJM Apr 2016target 2019
Gas project 51, Tooele County
Gas
31.0 MWWithdrawn / abandoned Tooele, UTWest Feb 2005target 2006
Other project G0426, Mason County
Other
31.0 MWWithdrawn / abandoned Mason, WAWest Apr 2010target 2013
East Towanda-South Troy 115 kV
Solar · Franklin Energy, LLC
31.0 MWWithdrawn / abandoned Bradford, PANYISO Sep 2025
Santos Solar
Solar
31.0 MWWithdrawn / abandoned Cumberland, NJPJM Apr 2020target 2023
Solar project AG2-220, Bradford County
Solar · Franklin Energy, LLC
31.0 MWWithdrawn / abandoned Bradford, PAPJM Jan 2025target 2025
Onshore wind project GEN-2011-034, Hall County
Onshore wind
31.0 MWWithdrawn / abandoned Hall, TXSPP Jun 2011target 2013
Liberty Gap WF
Onshore wind
31.0 MWWithdrawn / abandoned Pendleton, WVPJM Jul 2003target 2011
Replacing 31 MW of generation with linear generators powered by natural gas; Burlington 3
Gas
31.0 MWWithdrawn / abandoned Des Moines, IAMISO Dec 2023target 2024
LYNX Solar
Solar
30.9 MWWithdrawn / abandoned Santa Barbara, CACAISO May 2017target 2021
Hanson Energy Center
Battery storage
30.8 MWWithdrawn / abandoned Santa Barbara, CACAISO Apr 2020target 2023
Tatton Storage 1
Battery storage
30.6 MWWithdrawn / abandoned Mendocino, CACAISO Apr 2019target 2021
Apricot Energy Storage
Battery storage
30.6 MWWithdrawn / abandoned Fresno, CACAISO Apr 2020target 2023
Loriner Storage
Battery storage
30.5 MWWithdrawn / abandoned Santa Clara, CACAISO Apr 2019target 2022
Other project M06, Franklin County
Other
30.5 MWWithdrawn / abandoned Franklin, PAPJM Mar 2004target 2006
Shannon-1 Wind Farm Phase 1
Onshore wind · Shannon-1 Wind Farm, LLC
30.4 MWWithdrawn / abandoned ERCOT Jun 2009target 2050
Chelsea Energy Storage
Battery storage · Chelsea Road Energy Storage 1, LLC
30.4 MWWithdrawn / abandoned Richmond, NYNYISO Jun 2021
Helix Ravenswood I
Gas · LS Power Development, LLC
30.2 MWWithdrawn / abandoned New York, NYNYISO Oct 2017
Crowswest
Solar + storage
30.2 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2020target 2023
Solar project AG2-031, Stark County
Solar
30.2 MWWithdrawn / abandoned Stark, OHPJM Oct 2020target 2023
Solar project AH1-242, Clarion County
Solar
30.0 MWWithdrawn / abandoned Clarion, PAPJM Sep 2021target 2024
Mt Hope Waterpower Project
Other
30.0 MWWithdrawn / abandoned Morris, NJPJM Jun 2006target 2013
Biomass
Other
30.0 MWWithdrawn / abandoned Windsor, VTISO-NE Feb 2009target 2011
Gas project J914, Manistee County
Gas
30.0 MWWithdrawn / abandoned Manistee, MIMISO Jun 2017target 2019
Solar project 159B, Hamilton County
Solar · Masked
30.0 MWWithdrawn / abandoned Hamilton, FLSoutheast Oct 2016target 2021
Solar project 293-A, Weber County
Solar
30.0 MWWithdrawn / abandoned Weber, UTWest Sep 2009target 2012
Solar project IC-967, Lowndes County
Solar
30.0 MWWithdrawn / abandoned Lowndes, ALSoutheast Jun 2021
Solar project 1103, Iron County
Solar
30.0 MWWithdrawn / abandoned Iron, UTWest Jan 2019target 2022
Solar + storage project C3-049, Box Elder County
Solar + storage
30.0 MWWithdrawn / abandoned Box Elder, UTWest May 2023target 2025
Hydro project W2-005, Taylor County
Hydro
30.0 MWWithdrawn / abandoned Taylor, WVPJM May 2010target 2013
Solar project Q207, Pinal County
Solar
30.0 MWWithdrawn / abandoned Pinal, AZWest Oct 2011target 2013
Onshore wind project 2007-G11
Onshore wind
30.0 MWWithdrawn / abandoned West Dec 2007target 2010
Victor Grid Stabilization Project
Battery storage
30.0 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2014target 2016
Castle Gap Solar 2
Solar · Solar Prime
30.0 MWWithdrawn / abandoned ERCOT Sep 2014target 2020
Solar project IC-577, Hancock County
Solar
30.0 MWWithdrawn / abandoned Hancock, GASoutheast Jan 2017
Onshore wind project K24, Grant County
Onshore wind
30.0 MWWithdrawn / abandoned Grant, WVPJM Jul 2003target 2005
Weirton Solar 24 kV
Solar
30.0 MWWithdrawn / abandoned Hancock, WVPJM Jun 2020target 2024
Solar project 19, Hillsborough County
Solar
30.0 MWWithdrawn / abandoned Hillsborough, FLSoutheast Apr 2017target 2018
Battery storage project AG2-565, Fluvanna County
Battery storage
30.0 MWWithdrawn / abandoned Fluvanna, VAPJM Mar 2021target 2024
Battery storage project AG2-573, Buckingham County
Battery storage
30.0 MWWithdrawn / abandoned Buckingham, VAPJM Mar 2021target 2024
Battery storage project IA-PNM-2020-02, Bernalillo County
Battery storage
30.0 MWWithdrawn / abandoned Bernalillo, NMWest Jan 2020target 2022
Champlain Solar Uprate
Solar · RWE Clean Energy Development, LLC
30.0 MWWithdrawn / abandoned Washington, NYNYISO Sep 2024
Onshore wind project 2008-G4
Onshore wind
30.0 MWWithdrawn / abandoned West Feb 2008target 2012
Onshore wind project 2013-G2
Onshore wind
30.0 MWWithdrawn / abandoned West Apr 2013target 2014
Solar project AH1-572, Marion County
Solar · Swamp Fox Solar, LLC
30.0 MWWithdrawn / abandoned Marion, OHPJM Sep 2021target 2024
Solar project GI-2009-2, Alamosa County
Solar
30.0 MWWithdrawn / abandoned Alamosa, COWest Feb 2009target 2012
Hydro project AG2-172, Warren County
Hydro
30.0 MWWithdrawn / abandoned Warren, NJPJM Feb 2021target 2022
Other project 4, Elmore County
Other
30.0 MWWithdrawn / abandoned Elmore, IDWest Feb 2001target 2005
Page 356 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)