πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

GAS Β· WEST

Gas project 51, Tooele County

Gas project 51, Tooele County is a 31.0 MW gas request withdrawn in the West interconnection queue, in Tooele County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2005 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
51
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Rowley substation
Location
Tooele County, Utah
Technology
Gas: 31.0 MW
Total requested
31.0 MW
Service type
Network resource (NRIS)
Study phase
REMOVED-LACK OF PROGRESS
Queue status
Withdrawn
Entered queue
22 February 2005
Proposed online date
January 2006

Location

Marker shows the centre of Tooele County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Tooele County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem