Gas project 9, Tooele County

Gas project 9, Tooele County is a 80.0 MW gas request built and operating in the West interconnection queue, in Tooele County, Utah, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Apr 2001 (completed)
  2. ConsentedJul 2001 (completed)
  3. Construction (completed)
  4. OperatingTarget Jun 2001 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
9
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Desert Power, L.P.
Connection point (POI)
Rowley substation
Location
Tooele County, Utah
Technology
Gas: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
IA signed 7/9/01
Queue status
Operational
Entered queue
1 April 2001
Agreement signed
9 July 2001
Proposed online date
June 2001

Location

Marker shows the centre of Tooele County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Tooele County