United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in West (non-ISO utilities) — page 35

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,857519.1 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,857 requests · page 35 of 38
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project C2-11, Carbon County
Onshore wind · PacifiCorp
26.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Hydro project Q63, Kootenai County
Hydro
26.0 MWAgreement signed Kootenai, IDWest target 2028
Onshore wind project PIS050, Carbon County
Onshore wind · PacifiCorp
26.0 MWIn study Carbon, WYWest Feb 2024target 2024
Hydro project 63, Kootenai County
Hydro
26.0 MWAgreement signed Kootenai, IDWest Jun 2018target 2028
Solar project T2-079, Jefferson County
Solar
25.0 MWIn study Jefferson, ORWest Sep 2025target 2026
Onshore wind project G0827, Sherman County
Onshore wind
25.0 MWIn study Sherman, ORWest Dec 2022target 2024
Gas project T2-018, Utah County
Gas · PacifiCorp
25.0 MWIn study Utah, UTWest Aug 2025target 2026
Battery storage project G0832, Snohomish County
Battery storage
25.0 MWIn study Snohomish, WAWest Dec 2022target 2025
Solar + storage project T2-078, Modoc County
Solar + storage
24.9 MWIn study Modoc, CAWest Sep 2025target 2026
Gas project GI-2020-05, Weld County
Gas
24.0 MWAgreement signed Weld, COWest Mar 2020target 2020
Solar + storage project T2-088, Lake County
Solar + storage
23.5 MWIn study Lake, ORWest Sep 2025target 2027
Solar + storage project T2-042, Millard County
Solar + storage
20.0 MWIn study Millard, UTWest Sep 2025target 2027
Battery storage project G0734, Benton County
Battery storage
20.0 MWIn study Benton, WAWest Mar 2022target 2024
Solar project Q246, Yuma County
Solar
20.0 MWAgreement signed Yuma, AZWest Sep 2016target 2021
Solar + storage project T2-006, Tooele County
Solar + storage · PacifiCorp
20.0 MWIn study Tooele, UTWest Aug 2025target 2028
Solar + storage project T2-009, Umatilla County
Solar + storage
20.0 MWIn study Umatilla, ORWest Aug 2025target 2027
Geothermal project Company RA, Pershing County
Geothermal
20.0 MWIn study Pershing, NVWest Oct 2024target 2029
Solar + storage project 340, Yellowstone County
Solar + storage
20.0 MWIn study Yellowstone, MTWest Mar 2018target 2021
Solar + storage project T2-039, Emery County
Solar + storage
20.0 MWIn study Emery, UTWest Sep 2025target 2026
Solar project G1069, Harney County
Solar
20.0 MWIn study Harney, ORWest Jul 2024target 2025
Solar + storage project T2-044, Millard County
Solar + storage
20.0 MWIn study Millard, UTWest Sep 2025target 2027
Solar + storage project T2-045, Millard County
Solar + storage
20.0 MWIn study Millard, UTWest Sep 2025target 2027
Battery storage project G0830, Thurston County
Battery storage
20.0 MWIn study Thurston, WAWest Dec 2022target 2026
Solar + storage project T2-050, Lake County
Solar + storage
20.0 MWIn study Lake, ORWest Sep 2025target 2027
Solar + storage project T2-043, Millard County
Solar + storage
20.0 MWIn study Millard, UTWest Sep 2025target 2027
Solar project G0516, Sherman County
Solar
20.0 MWIn study Sherman, ORWest Oct 2015target 2016
Solar project 815, Emery County
Solar · Pivot 13, LLC
20.0 MWAgreement signed Emery, UTWest Nov 2016target 2025
Battery storage project G0942, Thurston County
Battery storage
20.0 MWIn study Thurston, WAWest Sep 2023target 2026
Solar project BHBE G22, Meade County
Solar
20.0 MWAgreement signed Meade, SDWest Oct 2022target 2024
Solar + storage project 25N-SG6, Lyon County
Solar + storage
20.0 MWIn study Lyon, NVWest Oct 2025target 2029
Battery storage project C2-209, Uintah County
Battery storage · Revolve Vernal BESS, LLC
20.0 MWPaused / redesign Uintah, UTWest May 2022target 2026
Solar project G0524, Wasco County
Solar
20.0 MWIn study Wasco, ORWest Jan 2016target 2018
Geothermal project Company RB, Lander County
Geothermal
20.0 MWIn study Lander, NVWest Oct 2024target 2029
Geothermal project T2-004, Sevier County
Geothermal
20.0 MWIn study Sevier, UTWest Aug 2025
Solar + storage project T2-048, Millard County
Solar + storage
20.0 MWIn study Millard, UTWest Sep 2025target 2027
Solar project G0570, Lake County
Solar
20.0 MWIn study Lake, ORWest Jul 2017target 2019
Geothermal project T2-005, Millard County
Geothermal
20.0 MWIn study Millard, UTWest Aug 2025
Geothermal project 25N-SG3, Humboldt County
Geothermal
20.0 MWIn study Humboldt, NVWest Aug 2025target 2030
Geothermal project T2-003, Millard County
Geothermal
20.0 MWIn study Millard, UTWest Aug 2025
Battery storage project G1058, Clark County
Battery storage
20.0 MWIn study Clark, WAWest Dec 2023target 2027
Geothermal project SGI-PNM-2025-01, Hidalgo County
Geothermal
20.0 MWIn study Hidalgo, NMWest Sep 2025target 2028
Solar project G0571, Lake County
Solar
20.0 MWIn study Lake, ORWest Jul 2017target 2019
Solar + storage project T2-010, Umatilla County
Solar + storage
20.0 MWIn study Umatilla, ORWest Aug 2025target 2027
Solar + storage project T2-049, Lake County
Solar + storage
20.0 MWIn study Lake, ORWest Sep 2025target 2027
Solar project TCS-52, Crook County
Solar · Get Along Solar II LLC
20.0 MWAgreement signed Crook, ORWest Apr 2020target 2026
Solar + storage project T2-047, Millard County
Solar + storage
20.0 MWIn study Millard, UTWest Sep 2025target 2027
Solar project G0537, Harney County
Solar
20.0 MWIn study Harney, ORWest May 2016target 2019
Solar project TCS-53, Crook County
Solar · Get Along Solar XI LLC
20.0 MWAgreement signed Crook, ORWest Apr 2020target 2026
Geothermal project 25N-SG5, Lander County
Geothermal
20.0 MWIn study Lander, NVWest Aug 2025target 2030
Solar project G0572, Lake County
Solar
20.0 MWIn study Lake, ORWest Jul 2017target 2019
Page 35 of 38

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)