United States › Grid › Interconnection queues › New Mexico
GEOTHERMAL · WESTGeothermal project SGI-PNM-2025-01, Hidalgo County
Geothermal project SGI-PNM-2025-01, Hidalgo County is a 20.0 MW geothermal request in interconnection study in the West interconnection queue, in Hidalgo County, New Mexico, connecting to Public Service Company of New Mexico.
- PlanningQueued Sep 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- SGI-PNM-2025-01
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company of New Mexico
- Connection point (POI)
- Lordsburg 115 KV substation
- Location
- Hidalgo County, New Mexico
- Technology
- Geothermal: 20.0 MW
- Total requested
- 20.0 MW
- Queue status
- Unknown
- Entered queue
- 22 September 2025
- Proposed online date
- May 2028
Location
Marker shows the centre of Hidalgo County; the queue data does not give exact sites.
Power plants in New Mexico · Transmission lines in New Mexico
Other requests in Hidalgo County
- Geothermal project SGI-PNM-2012-05, Hidalgo CountyGeothermal · 15.0 MW · built
- Solar + storage project IA-PNM-2021-14, Hidalgo CountySolar + storage · 200 MW · withdrawn
- Solar + storage project IA-PNM-2023-24, Hidalgo CountySolar + storage · 200 MW · withdrawn
- Solar project IA-PNM-2016-04, Hidalgo CountySolar · 80.0 MW · withdrawn
- Solar project SGI-PNM-2021-47, Hidalgo CountySolar · 5.0 MW · withdrawn
- Solar project SGI-PNM-2021-48, Hidalgo CountySolar · 5.0 MW · withdrawn
- Solar project SGI-PNM-2022-07, Hidalgo CountySolar · 5.0 MW · withdrawn
- Solar project SGI-PNM-2022-16, Hidalgo CountySolar · 5.0 MW · withdrawn
- Solar project SGI-PNM-2022-05, Hidalgo CountySolar · 5.0 MW · withdrawn
- Solar project SGI-PNM-2021-59, Hidalgo CountySolar · 5.0 MW · withdrawn
- Solar project SGI-PNM-2021-03, Hidalgo CountySolar · 5.0 MW · withdrawn
- Solar project SGI-PNM-2021-62, Hidalgo CountySolar · 5.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem