Solar project SGI-PNM-2021-03, Hidalgo County

Solar project SGI-PNM-2021-03, Hidalgo County is a 5.0 MW solar request withdrawn in the West interconnection queue, in Hidalgo County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedApr 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
SGI-PNM-2021-03
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
Lordsburg Substation Distribution Feeder 1000
Location
Hidalgo County, New Mexico
Technology
Solar: 5.0 MW
Total requested
5.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
5 April 2021
Proposed online date
October 2022
Withdrawn
April 2022

Location

Marker shows the centre of Hidalgo County; the queue data does not give exact sites.