Withdrawn queue requests in CAISO (California) — page 35

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,186619.9 GW
Active in queue188.6 GW429 requests
Agreement signed96.2 GW235 requests
Withdrawn2,186619.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,186 requests · page 35 of 44
ProjectCapacityStatusLocationRegionQueuedOnline
Wellhead Power Margarita
Gas
49.9 MWWithdrawn / abandoned Orange, CACAISO Feb 2007target 2010
Fairmont Solar I
Solar + storage
49.8 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2023
Midpoint Solar 2
Solar
49.5 MWWithdrawn / abandoned Riverside, CACAISO May 2008target 2012
Iron Mountain Solar 2
Solar
49.5 MWWithdrawn / abandoned Riverside, CACAISO May 2008target 2012
Borrego Solar 2
Solar
49.5 MWWithdrawn / abandoned San Diego, CACAISO May 2008target 2013
Iron Mountain Solar 1
Solar
49.5 MWWithdrawn / abandoned Riverside, CACAISO May 2008target 2012
Midpoint Solar 1
Solar
49.5 MWWithdrawn / abandoned Riverside, CACAISO May 2008target 2012
Waterman Mountains Wind Energy Project
Onshore wind
49.3 MWWithdrawn / abandoned San Bernardino, CACAISO May 2007target 2013
Wellhead Power Lilac
Gas
49.0 MWWithdrawn / abandoned San Diego, CACAISO May 2008target 2009
Wellhead Power Salado
Gas
49.0 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2008target 2009
Wellhead Power Ash Valley
Gas
49.0 MWWithdrawn / abandoned San Diego, CACAISO May 2008target 2009
Wellhead Power Rainbow
Gas
49.0 MWWithdrawn / abandoned San Diego, CACAISO May 2008target 2009
Wellhead Power Nella CHP
Gas
49.0 MWWithdrawn / abandoned Merced, CACAISO Apr 2012target 2014
Wellhead Power Lemietta CHP
Gas
49.0 MWWithdrawn / abandoned Kings, CACAISO Apr 2012target 2014
Wellhead Power Helm
Gas
49.0 MWWithdrawn / abandoned Fresno, CACAISO Apr 2008target 2009
Leprechaun
Gas
49.0 MWWithdrawn / abandoned Riverside, CACAISO Apr 2015target 2020
Wellhead Power Logan Creek
Gas
49.0 MWWithdrawn / abandoned Glenn, CACAISO May 2008target 2010
Wellhead Power Winters
Gas
49.0 MWWithdrawn / abandoned Yolo, CACAISO Apr 2008target 2009
Wellhead Power Firebaugh 2
Gas
49.0 MWWithdrawn / abandoned Fresno, CACAISO Apr 2008target 2009
Wellhead Power Kern 1
Gas
49.0 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2013
Wellhead Power Couser Canyon
Gas
49.0 MWWithdrawn / abandoned San Diego, CACAISO May 2008target 2009
Wellhead Power Woodland CHP
Gas
49.0 MWWithdrawn / abandoned Yolo, CACAISO Apr 2012target 2014
Wellhead Power Clemente
Gas
49.0 MWWithdrawn / abandoned Orange, CACAISO May 2008target 2009
Wellhead Power Lonestar
Gas
49.0 MWWithdrawn / abandoned San Diego, CACAISO May 2008target 2009
Puerta Solar Center
Solar
49.0 MWWithdrawn / abandoned Fresno, CACAISO Aug 2014target 2017
Wellhead Power Midfruit CHP
Gas
49.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2012target 2014
San Francisco Airport Electric Reliability Plant
Gas
48.7 MWWithdrawn / abandoned San Francisco, CACAISO Apr 2004target 2008
Colorado River 48 MW
Solar
48.0 MWWithdrawn / abandoned Riverside, CACAISO Mar 2011target 2014
Songs High Pressure Turbine Retrofit
Nuclear
48.0 MWWithdrawn / abandoned San Diego, CACAISO Jul 2009target 2012
Lost Hills Cogen
Gas
47.8 MWWithdrawn / abandoned Kern, CACAISO Apr 2013target 2017
Midway Hills Cogen
Gas
47.8 MWWithdrawn / abandoned Kern, CACAISO Apr 2013target 2017
Northern Pines
Solar + storage
47.6 MWWithdrawn / abandoned Lassen, CACAISO May 2016target 2022
Larkspur 3
Gas
47.4 MWWithdrawn / abandoned San Diego, CACAISO Nov 2006target 2016
Malaga BESS
Battery storage
46.3 MWWithdrawn / abandoned Fresno, CACAISO Jan 2023target 2024
Star GL Storage 2
Battery storage
45.8 MWWithdrawn / abandoned Sutter, CACAISO Apr 2018target 2021
Carrizo Solar Farm I
Solar
45.0 MWWithdrawn / abandoned San Luis Obispo, CACAISO Jul 2007target 2008
Centinela Solar Energy Expansion II - 45 MW Expansion
Solar
45.0 MWWithdrawn / abandoned Imperial, CACAISO Mar 2011target 2014
Ee Borrego II
Solar
45.0 MWWithdrawn / abandoned San Diego, CACAISO Mar 2011target 2015
Sunshine 3
Solar
45.0 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2014
Tehachapi Valley Solar I
Solar
45.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2012target 2016
Tierra Del Sol Solar Farm
Solar
45.0 MWWithdrawn / abandoned San Diego, CACAISO Mar 2011target 2016
KPP - 45
Gas
45.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2012target 2019
Big Break Energy Storage
Battery storage
45.0 MWWithdrawn / abandoned Contra Costa, CACAISO May 2017target 2021
California Bear 6
Solar + storage
44.8 MWWithdrawn / abandoned Fresno, CACAISO May 2017target 2021
Tobin
Solar + storage
44.4 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Appa Solar
Solar + storage
43.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Curry
Solar
42.2 MWWithdrawn / abandoned Fresno, CACAISO May 2016target 2020
Warriors
Solar
42.2 MWWithdrawn / abandoned Fresno, CACAISO May 2016target 2019
Santa Maria Energy BESS (Fka Santa Maria Energy Reliability Center)
Battery storage
42.0 MWWithdrawn / abandoned Santa Barbara, CACAISO Apr 2015target 2018
CPN Wild Horse Geothermal
Geothermal
42.0 MWWithdrawn / abandoned Sonoma, CACAISO Feb 2010target 2017
Page 35 of 44

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)