United States β€Ί Grid β€Ί Interconnection queues β€Ί California

BATTERY STORAGE Β· CAISO

Malaga BESS

Malaga BESS is a 46.3 MW battery storage request withdrawn in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2023 (completed)
  2. Withdrawn / abandonedNov 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2196
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Malaga 115 kV
Location
Fresno County, California
Technology
Battery: 46.3 MW
Total requested
46.3 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
4 January 2023
Proposed online date
November 2024
Withdrawn
November 2024

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem