GAS Β· CAISO

Wellhead Power Clemente

Wellhead Power Clemente is a 49.0 MW gas request withdrawn in the CAISO interconnection queue, in Orange County, California, connecting to SDGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2008 (completed)
  2. Withdrawn / abandonedNov 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
446
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Talega San Mateo 69kV line
Location
Orange County, California
Technology
Gas: 49.0 MW
Total requested
49.0 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 May 2008
Proposed online date
July 2009
Withdrawn
November 2008

Location

Marker shows the centre of Orange County; the queue data does not give exact sites.